Do you have any question about this error?
Message type: E = Error
Message class: KOPV - Messages for Plan Version Copying
Message number: 102
Message text: Year-independent unit costing not copied for object &1
Object &V1& is plan-integrated.
Target version &V2& is not defined for the current fiscal year in
controlling area &V3&. The system cannot decide whether the unit
costing is allowed for overall values because it uses the "Plan
integration with Cost Center Accounting" indicator from the version
settings for the current fiscal year.
Unit costing is not allowed if this indicator is set and the object is
plan-integrated.
The system does not copy the year-dependent unit costing for object
&V1& into target version &V2&.
Maintain the settings for the current fiscal year for version &V2& in
controlling area &V3&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
KOPV102
- Year-independent unit costing not copied for object &1 ?The SAP error message KOPV102 indicates that year-independent unit costing data could not be copied for a specific object (represented by &1). This error typically arises in the context of cost planning or cost object controlling when the system attempts to copy cost estimates or cost planning data but encounters issues with the year-independent unit costs.
Cause:
- Missing Data: The year-independent unit costs for the specified object may not be maintained in the system.
- Incorrect Configuration: There may be configuration issues in the controlling area or the cost object that prevent the copying of the unit costs.
- Object Type: The object type for which the costs are being copied may not support year-independent costing.
- Authorization Issues: The user may not have the necessary authorizations to access or copy the required costing data.
Solution:
- Check Costing Data: Verify that the year-independent unit costs are maintained for the object in question. You can do this by navigating to the relevant cost object and checking the cost estimates.
- Review Configuration: Ensure that the configuration settings for the controlling area and the specific cost object type are correct. This may involve checking the settings in the Customizing (SPRO) for Controlling.
- Update Costing: If the year-independent unit costs are missing, you may need to create or update the cost estimates for the object.
- Authorization Check: Ensure that the user has the necessary authorizations to perform the operation. This may involve checking user roles and permissions in the SAP system.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on the error message and related processes.
Related Information:
By following these steps, you should be able to identify the root cause of the KOPV102 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
KOPV101
Unit costing not permitted for plan-integrated object &1
What causes this issue? Unit costing is not allowed for WBS elements and internal orders which are plan integrated. Object &v1& in fiscal yea...
KOPV100
Unit costing
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
KOSA000
------------------------- General Messages ----------------------------
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
KOSA001
Characteristics entered do not match Controlling level
What causes this issue? The characteristics entered do not match the characteristics that the system expected based on the <DS:GLOS.36F138F91B385A...
Click on this link to search all SAP messages.