Do you have any question about this error?
Message type: E = Error
Message class: KJ - Cost Object Controlling for Make-to-Order Production
Message number: 138
Message text: WBS element & is flagged for deletion - no results analysis possible
The object is flagged for deletion.
<DS:GLOS.Results_analysis>Results analysis</> cannot be carried out.
If necessary, cancel the deletion flag.
Error message extract from SAP system. Copyright SAP SE.
KJ138
- WBS element & is flagged for deletion - no results analysis possible ?The SAP error message KJ138 indicates that a Work Breakdown Structure (WBS) element is flagged for deletion, which means that it cannot be used for results analysis. This typically occurs in project management within SAP, particularly in the context of controlling and financial reporting.
Cause:
- Flagged for Deletion: The WBS element has been marked for deletion in the system. This can happen if the project is being closed or if the WBS element is no longer needed.
- Inconsistent Data: There may be inconsistencies in the data related to the WBS element, such as incomplete postings or missing configurations.
- Project Closure: If the project associated with the WBS element is closed, the WBS may be flagged for deletion as part of the project closure process.
Solution:
Check Deletion Flag:
- Go to the WBS element in the SAP system and check if it is indeed flagged for deletion. You can do this by navigating to the WBS element in the Project System (PS) module.
- If it is flagged, you may need to remove the deletion flag if the WBS element is still required for reporting or analysis.
Remove Deletion Flag:
- To remove the deletion flag, you can use transaction code
CJ02
(Change WBS Element) and uncheck the deletion flag.- Ensure that you have the necessary authorizations to make this change.
Review Project Status:
- If the project is closed, consider whether you need to reopen it or if you can create a new WBS element for ongoing activities.
Consult with Project Management:
- Discuss with your project management team to understand the implications of removing the deletion flag and whether the WBS element should be retained or permanently deleted.
Check for Open Items:
- Ensure that there are no open items or transactions that are still linked to the WBS element. If there are, you may need to resolve these before you can proceed.
Related Information:
CJ01
(Create WBS Element), CJ02
(Change WBS Element), and CJ03
(Display WBS Element).By following these steps, you should be able to resolve the KJ138 error and proceed with your results analysis as needed.
Get instant SAP help. Start your 7-day free trial now.
KJ137
No item -> valuation type undefined
What causes this issue? No item exists for the run schedule header.System Response <DS:GLOS.WIP_calculation>WIP calculation</> is not po...
KJ136
This item has a separate cost collector
What causes this issue? The run schedule header item can carry costs. <DS:GLOS.WIP_calculation>WIP calculation</> for run schedule header...
KJ139
Project & is flagged for deletion
What causes this issue? The project is flagged for deletion.System Response You can no longer process the project.How to fix this error? If necessa...
KJ140
Collective order & is activity-assigned
What causes this issue? The network order is activity-assigned. <DS:GLOS.WIP_calculation>WIP calculation</> cannot be carried out for suc...
Click on this link to search all SAP messages.