Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 076
Message text: Dist. key & can only be used for cost centers or business processes.
You have selected distribution key &V1& for an order, a WBS element, a
cost object or a real estate object. However, this distribution key
distributes analogously to an activity quantity that was planned on a
cost center or business process.
It can therefore only be used with activity-dependent cost center
planning or when planning business processes.
The entry is not accepted.
Select another, suitable distribution key.
Error message extract from SAP system. Copyright SAP SE.
K8076
- Dist. key & can only be used for cost centers or business processes. ?The SAP error message K8076 indicates that the distribution key you are trying to use is restricted to cost centers or business processes. This error typically arises when you attempt to use a distribution key that is not compatible with the type of object you are working with, such as internal orders or projects.
Cause: Incorrect Distribution Key: The distribution key you are using is defined in the system to be applicable only for cost centers or business processes, but you are trying to apply it to a different type of object (like an internal order).
Configuration Issues: The distribution key may not be properly configured in the system to allow its use with the object type you are working with. Master Data Issues: The master data for the object you are trying to use may not be set up correctly to support the distribution key.
Solution: Check Distribution Key: Verify that the distribution key you
Get instant SAP help. Sign up for our Free Essentials Plan.
K8075
Distribution key & can only be used with activity-dependent records
What causes this issue? You have selected distribution key &V1& for planning on cost center &V2&. However, this distribution key dist...
K8074
Statistical cost element & can only be planned activity independent
What causes this issue? Within planning, you have created a new line that contains both an activity type and a cost element. Cost element &V1&...
K8077
Dist. key & can only be used in cost element/stat. key fig. planning
What causes this issue? You have selected distribution key &V1& for an activity type planning. However, this distribution key distributes ana...
K8078
No errors have occurred so far during the deletion check.
What causes this issue? You have chosen 'Extras -> Error log -> Delete...' to display the reason why a planning record could not be d...
Click on this link to search all SAP messages.