Do you have any question about this error?
Message type: E = Error
Message class: IW - Order Processing
Message number: 552
Message text: Profit center in order different to default entry
The <GL:maintenance_order>maintenance order</> has a
<GL:profit_center>profit center</> that does not correspond with that
proposed by the system from the <GL:cost_center>cost center</> of the
<GL:main_work_center>main work center</>.
This may be because
the main work center of the maintenance order has been changed
the profit center of the maintenance order has been changed
The system will <ZH>not</> automatically change the data.
Check whether the required profit center is valid for the maintenance
order and change it if necessary.
Error message extract from SAP system. Copyright SAP SE.
IW552
- Profit center in order different to default entry ?The SAP error message IW552 indicates that there is a discrepancy between the profit center assigned to a specific order and the default profit center that is set in the system. This error typically occurs in the context of maintenance orders or production orders when the system expects the profit center to match the default entry but finds a different one.
Cause:
- Profit Center Assignment: The order has a profit center assigned that does not match the default profit center defined for the order type or the relevant cost center.
- Configuration Issues: There may be configuration settings in the order type or the controlling area that are not aligned with the profit center settings.
- Manual Entry: A user may have manually entered a profit center that is not consistent with the default settings.
Solution:
- Check Order Settings: Review the order in question to see what profit center is assigned. Compare it with the default profit center for that order type.
- Adjust Profit Center: If the profit center assigned to the order is incorrect, you can change it to match the default profit center.
- Review Configuration: Check the configuration settings for the order type in the SAP system. Ensure that the default profit center is correctly set up in the relevant configuration areas (e.g., in the order type settings).
- Cost Center Assignment: Ensure that the cost center associated with the order is correctly assigned to the appropriate profit center.
- Consult Documentation: If necessary, refer to SAP documentation or consult with your SAP administrator for specific configuration settings related to profit centers and orders.
Related Information:
By following these steps, you should be able to resolve the IW552 error and ensure that the profit center assignments are consistent across your orders.
Get instant SAP help. Start your 7-day free trial now.
IW551
The order has no settlement rule
What causes this issue? You tried to display the <GL:settlement_rule>settlement rule</> for the <GL:maintenance_order>PM order</...
IW550
*** Functions Part 2 ***
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IW553
Assignment f. capital investment program not possible, project maintained
What causes this issue? You want to assign the order to a <DS:GLOS.capital_investment_program>capital investment program</>. This is not ...
IW554
Please maintain settlement rule
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.