Do you have any question about this error?
Message type: E = Error
Message class: IW - Order Processing
Message number: 059
Message text: Enter the plant for the main work center
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
IW059
- Enter the plant for the main work center ?The SAP error message IW059 ("Enter the plant for the main work center") typically occurs in the context of work order creation or maintenance in the SAP system, particularly within the Plant Maintenance (PM) or Production Planning (PP) modules. This error indicates that the system requires a plant assignment for the main work center associated with the operation in the work order.
Cause:
The error arises when:
- The main work center defined in the operation of the work order does not have a plant assigned to it.
- The work center is not properly configured in the system.
- The work center may exist, but it is not linked to any plant in the configuration.
Solution:
To resolve the IW059 error, follow these steps:
Check Work Center Configuration:
- Go to the transaction code
CR02
(Change Work Center).- Enter the work center ID that is causing the error.
- Verify that the work center is assigned to the correct plant. If not, you will need to assign it to the appropriate plant.
Assign Plant to Work Center:
- If the work center is not assigned to any plant, you can do this by:
- Selecting the "Basic Data" tab.
- Entering the relevant plant in the "Plant" field.
- Save the changes.
Verify Work Order:
- After making the necessary changes to the work center, go back to the work order (transaction code
IW32
for change orIW31
for create).- Ensure that the main work center is correctly specified in the operations of the work order.
Check for Other Errors:
- If the error persists, check for any other related configuration issues or missing data in the work order or work center.
Related Information:
By following these steps, you should be able to resolve the IW059 error and proceed with your work order processing in SAP.
Get instant SAP help. Start your 7-day free trial now.
IW058
Confirm manual change of work center before assigning service type
What causes this issue? You have entered a new work center for an existing operation. It is therefore advisable to assign an <DS:GLOS.maintenance_...
IW057
Cost center assignment to main work center has not been maintained
What causes this issue? No cost center allocation was maintained for <GL:work_center>work center</> &v1& that you entered in the ...
IW060
No WBS element is assigned to the order
What causes this issue? You want to assign a component to a project stock. However, this is not possible, as you have not assigned a corresponding WB...
IW061
No sales order is assigned to the order
What causes this issue? You want to assign a component to sales order stock. However, this is not possible as you have not assigned any corresponding...
Click on this link to search all SAP messages.