Message text: Maintenance plan & was not scheduled
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
IP734
- Maintenance plan & was not scheduled ?The SAP error message IP734 indicates that a maintenance plan was not scheduled due to certain issues. This error typically arises in the context of SAP Plant Maintenance (PM) when trying to schedule maintenance tasks or plans. Here are some common causes, solutions, and related information for this error:
Causes:
- Missing or Incorrect Data: The maintenance plan may have missing or incorrect data, such as invalid start dates, end dates, or scheduling parameters.
- Scheduling Parameters: The scheduling parameters for the maintenance plan may not be set correctly, leading to issues in generating the maintenance orders.
- Status of the Maintenance Plan: The maintenance plan might be in a status that does not allow scheduling (e.g., inactive).
- Calendar Issues: There may be issues with the factory calendar or holiday calendar that affect the scheduling of maintenance tasks.
- Dependencies: There could be dependencies on other maintenance plans or tasks that are not met.
- Capacity Constraints: If there are capacity constraints in the system, it may prevent the scheduling of the maintenance plan.
Solutions:
- Check Maintenance Plan Data: Review the maintenance plan for any missing or incorrect data. Ensure that all required fields are filled out correctly.
- Review Scheduling Parameters: Verify the scheduling parameters and ensure they are set correctly for the maintenance plan.
- Check Status: Ensure that the maintenance plan is active and not in a status that prevents scheduling.
- Review Calendar Settings: Check the factory calendar and holiday calendar settings to ensure they are configured correctly and do not conflict with the maintenance plan.
- Check Dependencies: Investigate any dependencies that may be affecting the scheduling of the maintenance plan and resolve them.
- Capacity Planning: Review capacity planning and ensure that there are no constraints that would prevent the scheduling of the maintenance tasks.
Related Information:
By following these steps, you should be able to identify the cause of the IP734 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
IP733
Calculated date is after end of factory calendar &1; maintenance plan &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IP732
Date &1 is before the start of factory calendar &2; Maint. plan &3
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IP735
Maintenance plan & was not scheduled in Parallel Processing
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IP736
Enter an end date for scheduling that is after the start of cycle date