Message text: Scheduling will occur with a start offset
You have tried to schedule the
<GL:preventive_maintenance_plan>maintenance plan</> for the first time.
Since a <GL:start_offset>start offset</> has been assigned to a
maintenance cycle, the offset is used for calculating the first planned
date.
The planned dates of the <GL:maintenance_cycle>maintenance cycles</>
<ZH>without</> a start offset will be calculated depending on the
operation type as follows:
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
OR operation:,,Planned date: 12.31.9999Error message extract from SAP system. Copyright SAP SE.
IP449
- Scheduling will occur with a start offset ?The SAP error message IP449 indicates that scheduling will occur with a start offset. This message typically arises in the context of production planning and scheduling within the SAP system, particularly when dealing with planned orders, production orders, or maintenance plans.
Cause: The error message IP449 is usually triggered when the system detects that the scheduling of a task (like a production order or maintenance task) cannot start at the originally planned time due to constraints such as: Resource Availability: The required resources (machines, labor, etc.) are not available at the planned start time. Capacity Constraints: There may be capacity issues that prevent the task from starting on time. Dependencies: There may be dependencies on other tasks or orders that have not been completed yet. Time Constraints: The defined time windows for the task may not align with the available scheduling slots.
Solution: To resolve the IP449 error, consider the following steps: Check Resource Availability: Ensure that the necessary
Get instant SAP help. Sign up for our Free Essentials Plan.
IP448
No counter reading entered yet for unit, & measuring point &
What causes this issue? The <GL:counter>counter</> data has not been fully maintained for <GL:maintenance_plan_scheduling>schedulin...
IP447
No annual performance entered for measuring point &
What causes this issue? The <GL:measuring_point>measuring point</> has been defined as a <GL:counter>counter</>. If a counter...
IP450
Scheduling will be performed based on current counter readings : &
What causes this issue? You have tried to perform initial or <DS:GLOS.maintenance_plan_scheduling>further scheduling</> of the <GL:pre...
IP451
No active maintenance cycles exist
What causes this issue? You are trying to schedule a maintenance plan that has no active <GL:maintenance_cycle>maintenance cycles</>.Syst...