Do you have any question about this error?
Message type: E = Error
Message class: GRPG - Grouping/Pegging for Individual Project Planning
Message number: 121
Message text: WBS element has not assigned a valuated individual stock
Project stock is not available for WBS element &v1&. A WBS element has
to have project stock, to talke part in requirements grouping.
Make sure that valuated project stock has been selected in the
<DS:TRAN.CJ07>Project definition</> of the WBS element. If the project
has already been saved with non-valuated project stock or even without
project stock, you cannot use WBS elements from this project for
requirements grouping.
Error message extract from SAP system. Copyright SAP SE.
GRPG121
- WBS element has not assigned a valuated individual stock ?The SAP error message GRPG121 indicates that a Work Breakdown Structure (WBS) element has not been assigned a valuated individual stock. This typically occurs in the context of project management and controlling within SAP, particularly when dealing with project-related materials and inventory.
Cause:
- Missing Assignment: The WBS element is not linked to any valuated individual stock. This means that the system cannot find any stock that is specifically assigned to that WBS element.
- Incorrect Configuration: The configuration settings for the project or the materials may not be set up correctly, leading to the inability to assign stock to the WBS element.
- Stock Type: The stock type may not be compatible with the WBS element. For example, if the stock is not marked as valuated or is in a non-usable state, it cannot be assigned.
- Project Settings: The project settings may not allow for the assignment of individual stock to the WBS element.
Solution:
- Check WBS Element Assignment: Ensure that the WBS element is correctly assigned to the relevant project and that it is set up to accept valuated individual stock.
- Assign Valuated Stock: If there is stock available, ensure that it is properly assigned to the WBS element. This can be done through the transaction codes related to project stock management (e.g., using the transaction code
MB1A
for goods issues).- Review Material Master Data: Check the material master data to ensure that the stock is set up as valuated and that it is compatible with the WBS element.
- Configuration Settings: Review the configuration settings in the project system (PS) module to ensure that the settings allow for the assignment of individual stock to WBS elements.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing project stock and WBS elements.
Related Information:
CJ20N
(Project Builder), CJI3
(Project Actual Line Items), and MB1A
(Goods Withdrawal) for managing project-related stock.By following these steps, you should be able to resolve the GRPG121 error and successfully assign valuated individual stock to the relevant WBS element.
Get instant SAP help. Start your 7-day free trial now.
GRPG120
You cannot assign a grouping WBS element to itself
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
GRPG115
Could not assign a grouping WBS element using collective processing
What causes this issue? Using the collective processing transaction, you have tried to assign grouping WBS element &v1& to another grouping W...
GRPG122
WBS element & has been assigned to an incorrect controlling area
What causes this issue? WBS element &v1& is assigned to another controlling area than the grouping WBS element. Thre WBS elements within a gr...
GRPG123
This assignment causes an inconsistency in the group hierarchy
What causes this issue? Recursive group structures are not allowed. You treis to assign a grouping WBS element to another grouping WBS element, which...
Click on this link to search all SAP messages.