How To Fix GPD2039 - No MRP Group for plant &1, material &2. Replenishment &3 &4 not pegged.


SAP Error Message - Details

  • Message type: E = Error

  • Message class: GPD2 - GPD for DIMP4.71 uses message class GPD & GPD2

  • Message number: 039

  • Message text: No MRP Group for plant &1, material &2. Replenishment &3 &4 not pegged.

  • Show details Hide details
  • What causes this issue?

    There is no MRP Group defined for the plant &1 and material
    &2 combination. For this reason, the replenishment object
    &3 &4 has not been pegged.

    System Response

    In order to consider a replenishment object for pegging, you must
    define MRP Group for the material and plant combination of that
    replenishment.
    It could be that the replenishment object is in a plant where it should
    not be. Please also check the plant of this replenishment object.

    How to fix this error?

    First, you must check to see that the plant &1 is relevant for
    GPD processes.
    If the plant is not relevant for GPD, then pegging will not peg any
    replenishments from this plant, to any requirements in this plant.
    If you still wish to peg this replenishment, then you must <ZH>either
    move the replenishment to another plant that is relevant for pegging,
    or define an MRP Group for the plant / material combination in
    question. </>
    You can define the MRP Group for the material using the Material
    Master.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message GPD2039 - No MRP Group for plant &1, material &2. Replenishment &3 &4 not pegged. ?

    The SAP error message GPD2039 indicates that there is no MRP (Material Requirements Planning) group assigned for a specific plant and material combination. This error typically arises during the planning process when the system attempts to perform MRP calculations but cannot find the necessary configuration for the specified material in the given plant.

    Cause:

    1. Missing MRP Group: The most common cause is that the material does not have an MRP group assigned in the material master data.
    2. Incorrect Plant Configuration: The plant may not be properly configured to use the specified MRP group.
    3. Material Master Data Issues: The material master record may be incomplete or incorrectly set up, particularly in the MRP views.
    4. Replenishment Strategy: The replenishment strategy for the material may not be set up correctly, leading to issues in pegging.

    Solution:

    1. Check Material Master Data:

      • Go to the material master record (transaction code MM03).
      • Check the MRP views (MRP 1, MRP 2, etc.) to ensure that an MRP group is assigned.
      • If not, you can assign an appropriate MRP group using transaction code MM02.
    2. Assign MRP Group:

      • If the MRP group is missing, you can assign it by editing the material master data.
      • Ensure that the MRP group is valid and exists in the system.
    3. Verify Plant Configuration:

      • Ensure that the plant is correctly set up to use the MRP group.
      • Check the configuration in the customizing settings (transaction code SPRO) under the MRP settings.
    4. Review Replenishment Strategy:

      • Check the replenishment strategy assigned to the material and ensure it is compatible with the MRP group.
      • Adjust the replenishment strategy if necessary.
    5. Run MRP Again:

      • After making the necessary changes, run the MRP process again to see if the error persists.

    Related Information:

    • MRP Groups: MRP groups are used to categorize materials for planning purposes. They determine how the MRP process will handle the material, including planning parameters and strategies.
    • Material Master Views: The material master has several views, and the MRP views are crucial for MRP processing. Ensure that all relevant fields are filled out correctly.
    • Transaction Codes:
      • MM03: Display Material Master
      • MM02: Change Material Master
      • MD01: MRP Run
      • SPRO: Customizing settings

    By following these steps, you should be able to resolve the GPD2039 error and ensure that your MRP process runs smoothly.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker