Do you have any question about this error?
Message type: E = Error
Message class: GPD - Pegging & Distribution
Message number: 060
Message text: Stock material &, grouping WBS element & could not be distributed
Stock for material &V1&, grouping WBS element &V1& could not be
distributed.
Please check whether you have already performed
<DS:GLOS.3D7F5C64BE0BD511BCBC0800060D9C68>pegging</> (transaction
PEG01N). The subsequent cost distribution is based on the assignments
that are made during pegging.
A further reason can be that goods receipt for material &V1& has taken
place for reference to a purchase order or a production order. In this
case, the operation is not taken into account during cost distribution.
Please check this using the stock overview (transaction PEG07).
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
GPD060
- Stock material &, grouping WBS element & could not be distributed ?The SAP error message GPD060 typically indicates that there is an issue with the distribution of stock materials related to a specific grouping WBS (Work Breakdown Structure) element. This error can occur in the context of project systems (PS) or when dealing with project-related stock materials in SAP.
Cause:
- Missing or Incorrect Configuration: The WBS element may not be properly configured to allow for the distribution of stock materials.
- Stock Availability: There may be insufficient stock available for the material that is being distributed.
- Incorrect Assignment: The stock material may not be correctly assigned to the WBS element or project.
- Status of WBS Element: The WBS element might be in a status that does not allow for distribution (e.g., it could be locked or closed).
- Authorization Issues: The user may not have the necessary authorizations to perform the distribution for the specified WBS element.
Solution:
- Check WBS Configuration: Ensure that the WBS element is correctly configured to allow for stock distribution. This includes checking the settings in the project definition and ensuring that the WBS element is active.
- Verify Stock Levels: Check the stock levels for the material in question to ensure that there is enough available stock to distribute.
- Review Material Assignment: Confirm that the stock material is correctly assigned to the WBS element. You can do this by checking the material master data and the project structure.
- WBS Status: Check the status of the WBS element. If it is locked or closed, you may need to change its status to allow for distribution.
- Authorization Check: Ensure that the user has the necessary authorizations to perform the distribution. This may involve checking user roles and permissions in SAP.
- Consult SAP Notes: Look for any relevant SAP Notes that may address this specific error message or provide additional troubleshooting steps.
Related Information:
By following these steps, you should be able to identify the root cause of the GPD060 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
GPD059
Stock difference for object & could not be assigned
What causes this issue? Stock difference for object &V1& could not be assigned.System Response In a subsequent cost distribution, the object...
GPD058
Surplus for object & could not be assigned
What causes this issue? Scrap for object &V1& could not be assigned.System Response The costs for the object cannot be completely distribute...
GPD061
Material & in plant & is irrelevant for requirements grouping
What causes this issue? Material &V1& has not been defined as relevant for the requirements grouping in plant &V2&.System Response T...
GPD062
Break points are not supported for valuated stock
What causes this issue? The indicator for valuated stock has been set in the appropriate project definition. Due to the synchronous quantity and valu...
Click on this link to search all SAP messages.