How To Fix GJ629 - Equity Group for Project & Has Changed from & to &


SAP Error Message - Details

  • Message type: E = Error

  • Message class: GJ - Joint Venture Accounting

  • Message number: 629

  • Message text: Equity Group for Project & Has Changed from & to &

  • Show details Hide details
  • What causes this issue?

    The equity group retrieved from T8J4B is different then the equity
    group on T8JG.

    System Response

    Cash call is blocked.

    How to fix this error?

    Determine which equity group is correct and modify the cash call.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message GJ629 - Equity Group for Project & Has Changed from & to & ?

    The SAP error message GJ629 indicates that there has been a change in the equity group for a project. This typically occurs in the context of project accounting and can affect how costs and revenues are allocated to different equity groups.

    Cause:

    The error message GJ629 is triggered when there is an inconsistency in the equity group assignment for a project. This can happen due to various reasons, such as:

    • Manual changes to the project settings that alter the equity group.
    • Changes in the project structure or hierarchy that affect the equity group assignment.
    • Data migration or updates that inadvertently change the equity group.

    Solution:

    To resolve the GJ629 error, you can take the following steps:

    1. Check Project Settings:

      • Navigate to the project in question and verify the equity group assignment. Ensure that it is correctly set according to your organizational requirements.
    2. Review Changes:

      • If there have been recent changes to the project or its structure, review those changes to understand why the equity group has been altered.
    3. Reassign Equity Group:

      • If the equity group needs to be changed back to the original value, you can do this through the project management transaction (e.g., CJ02 for changing project definitions).
    4. Consult Documentation:

      • Check any relevant documentation or change logs to see if there were any planned changes that might have affected the equity group.
    5. Contact Support:

      • If you are unable to resolve the issue, consider reaching out to your SAP support team or consulting SAP notes for any known issues related to this error.

    Related Information:

    • Transaction Codes: Familiarize yourself with relevant transaction codes such as CJ02 (Change Project), CJ03 (Display Project), and CJ20N (Project Builder) for managing project definitions and structures.
    • SAP Notes: Look for SAP Notes that may provide additional insights or patches related to this error message.
    • User Authorization: Ensure that you have the necessary authorizations to make changes to project settings, as lack of permissions can also lead to issues.

    By following these steps, you should be able to identify the cause of the GJ629 error and implement a solution to resolve it.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant