How To Fix G01810 - Target assignments are not identical for equivalent tasks


SAP Error Message - Details

  • Message type: E = Error

  • Message class: G01 - SAP Consolidation

  • Message number: 810

  • Message text: Target assignments are not identical for equivalent tasks

  • Show details Hide details
  • What causes this issue?

    You have defined multiple reclassification tasks for which you have
    selected the <LS>Assets Held for Sale</> checkbox.
    For any reclassification tasks that have the same setting for <LS>Assets
    Held for Sale</> and <LS>Value Allowance of Assets/Liabilities</> and
    the same setting for <LS>Processing of Assets Held for Sale</> in the
    assigned reclassification method, you must define the same target
    assignment in all steps of the reclassification method.
    Exception: If you have chosen the value <LS>Consolidation Units Held for
    Sale</> for <LS>Processing of Assets Held for Sale</>, it is useful to
    use two different target assignments for assets or liabilities held for
    sale.

    System Response

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    How to fix this error?

    Adjust the Customizing settings for the target assignments of the
    respective reclassification method s as described above.

    Procedure for System Administrators


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message G01810 - Target assignments are not identical for equivalent tasks ?

    The SAP error message G01810, which states "Target assignments are not identical for equivalent tasks," typically occurs in the context of project management or task assignment within SAP systems, particularly in the Project System (PS) module. This error indicates that there is a mismatch in the target assignments for tasks that are considered equivalent.

    Cause:

    The error usually arises due to one of the following reasons:

    1. Inconsistent Target Assignments: When you have multiple tasks that are equivalent (i.e., they are part of the same project or have similar characteristics), they should have the same target assignments. If one task has a different target assignment than the others, this error will be triggered.

    2. Changes in Task Configuration: If the configuration of tasks has been altered (e.g., changes in the work breakdown structure or task dependencies), it may lead to inconsistencies in target assignments.

    3. Data Entry Errors: Manual data entry errors can also lead to discrepancies in target assignments.

    Solution:

    To resolve the G01810 error, you can follow these steps:

    1. Check Target Assignments: Review the target assignments for the equivalent tasks that are causing the error. Ensure that they are consistent across all equivalent tasks.

    2. Adjust Assignments: If you find discrepancies, adjust the target assignments so that they match for all equivalent tasks. This may involve changing the target assignment of one or more tasks to ensure uniformity.

    3. Review Task Configuration: If the error persists, review the configuration of the tasks involved. Ensure that they are set up correctly and that any changes made to the project structure are reflected in the task assignments.

    4. Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing target assignments in your version of SAP.

    5. Seek Help from SAP Support: If you are unable to resolve the issue, consider reaching out to SAP support or your internal SAP team for further assistance.

    Related Information:

    • Transaction Codes: You may need to use transaction codes like CJ20N (Project Builder) or CJ02 (Change Project) to view and modify project tasks and their assignments.
    • Project System (PS) Module: Familiarize yourself with the functionalities of the Project System module in SAP, as understanding how tasks and assignments work will help in troubleshooting similar issues in the future.
    • User Roles and Authorizations: Ensure that you have the necessary authorizations to make changes to project tasks and assignments.

    By following these steps, you should be able to identify and correct the cause of the G01810 error in your SAP system.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant