Message type: E = Error
Message class: FINS_REV_REC - Event Based revenue recognition
Message number: 010
Message text: Maintain plan costs suitable for &2 using revenue recognition method '&1'
The method which is used for revenue recognition needs plan costs in
order to function.
Example
The cost based percentage-of-completion (POC) method for an item with a
fix price agreement would calculate
POC = actual costs / plan costs
Recognized revenue = POC * plan revenue
Without plan costs the cost based POC method cannot be applied. And of
course here you also would need suitable plan revenues.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Please maintain suitable plan costs for the quoted object.
If plan costs are maintained and the error message is still displayed,
please check the customizing of event based revenue recognition. Verify
whether the right plan source has been selected and verify whether all
relevant cost elements or condition types are assigned to sources with
suitable usages.
With the app "Run Revenue Recognition - Projects" respective transaction
REV_REC_COL_PRO you may verify the assignment of cost elements and
condition types. Choose Execution Type "Display" and execute. On the
result list select the line of the WBS element you are interested in. On
the document which is displayed then you search for the section "List of
applied assignment rules". The same procedure applies to other object
types using the appropriate app respective transaction.
Public Cloud
The app "Plan Customer Projects" will create plan costs for customer
projects if you plan labor and expenses under the tab "Work Packages".
Plan revenue will be created if you maintain the billing plan under the
tab "Billing".
With the app "Revenue Recognition (Event Based) - Projects" you also may
verify the assignment of cost elements and condition types. There you
select the details for a certain WBS element, then you execute the
action "Revalue" and on the window which then pops up you select the
action "Explain Simulation". On the document which is displayed then you
search for the section "List of applied assignment rules".
Error message extract from SAP system. Copyright SAP SE.
FINS_REV_REC010
- Maintain plan costs suitable for &2 using revenue recognition method '&1' ?The SAP error message FINS_REV_REC010 typically occurs in the context of revenue recognition in SAP, particularly when dealing with the planning of costs associated with a project or sales order. This error indicates that the plan costs for a specific revenue recognition method are not maintained correctly.
Cause:
The error message is triggered when:
- The revenue recognition method specified (indicated by '&1') does not have corresponding plan costs defined for the project or sales order (indicated by '&2').
- The system requires that plan costs be maintained for the revenue recognition method being used, but they are either missing or incorrectly configured.
Solution:
To resolve this error, you can take the following steps:
Check Revenue Recognition Method:
- Go to the configuration settings for revenue recognition methods in SAP (Transaction code: OAA3 or similar).
- Verify that the revenue recognition method you are using is correctly set up and that it is appropriate for the type of project or sales order.
Maintain Plan Costs:
- Navigate to the relevant project or sales order in SAP.
- Ensure that plan costs are maintained for the project or sales order. This can typically be done in the project planning or sales order management screens.
- If plan costs are not maintained, enter the necessary data to ensure that they align with the revenue recognition method.
Review Configuration Settings:
- Check the configuration settings for the project or sales order type to ensure that they are compatible with the revenue recognition method.
- Make sure that all necessary settings related to cost planning and revenue recognition are correctly configured.
Consult Documentation:
- Review SAP documentation or help files related to revenue recognition and cost planning for additional guidance on how to set up and maintain these elements.
Testing:
- After making the necessary changes, test the process again to ensure that the error no longer occurs.
Related Information:
By following these steps, you should be able to resolve the FINS_REV_REC010 error and ensure that your revenue recognition processes function smoothly.
Get instant SAP help. Start your 7-day free trial now.
FINS_REV_REC009
Assignment rule &3: GL account &2 ist a cost element in CO area &1
What causes this issue? The quoted GL account which is provided by the quoted source assignment and posting rule of event based revenue recognition i...
FINS_REV_REC008
Maintain all accounts for chart of acc. &1 assignment rule/no &2/&3
What causes this issue? The quoted source assignment and posting rule does not proved all requested GL accounts.System Response The system issues an...
FINS_REV_REC011
Update of Revenue recognition key to master data failed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
FINS_REV_REC012
Positive values for revenues ("negative revenues") are not supported
What causes this issue? For customer contract items like a sales order item or a contract item in a customer project it is expected, that the amount ...
Click on this link to search all SAP messages.