Do you have any question about this error?
Message type: E = Error
Message class: FCO_AVC_CC - Availability Control: Cost Centers
Message number: 102
Message text: Tolerance limit of &2% for cost center &1 has been reached in FY &3.
If you change the budget for cost center &V1& in fiscal year &V3&, the
budget tolerance limit of &V2&% for the account group &V4& would be
exceeded.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
FCO_AVC_CC102
- Tolerance limit of &2% for cost center &1 has been reached in FY &3. ?The SAP error message FCO_AVC_CC102 indicates that a tolerance limit for a cost center has been reached in a specific fiscal year. This message is part of the Availability Control (AVC) functionality in SAP, which is used to monitor and control budget consumption against predefined limits.
Cause:
The error occurs when the actual costs or commitments for a cost center exceed the defined tolerance limit (in this case, &2%) for a specific fiscal year (&3). This is a safeguard to prevent overspending beyond the budgeted amount.
Solution:
To resolve this error, you can take the following steps:
Review the Tolerance Limit:
- Check the tolerance limit settings for the cost center in question. You can do this by navigating to the relevant configuration in SAP (usually in the controlling module).
- If necessary, adjust the tolerance limit to allow for higher spending, but ensure that this aligns with your organization's financial policies.
Analyze Cost Center Usage:
- Review the actual costs and commitments associated with the cost center to understand why the limit has been reached.
- Identify any unexpected expenses or commitments that may have contributed to the situation.
Adjust Budget:
- If the costs are justified and necessary, consider adjusting the budget for the cost center to accommodate the increased spending.
Consult with Stakeholders:
- Discuss with relevant stakeholders (e.g., budget owners, finance team) to determine if the spending is appropriate and if any corrective actions are needed.
Monitor Future Transactions:
- Implement monitoring processes to keep track of costs and commitments against the budget to prevent similar issues in the future.
Related Information:
Transaction Codes:
Configuration Settings:
Documentation:
User Roles:
By following these steps, you should be able to address the error message and manage the cost center effectively.
Get instant SAP help. Start your 7-day free trial now.
FCO_AVC_CC100
---------- Plan Data Checks ----------
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
FCO_AVC_CC014
Availability control is active and "Lock Commitment Updates" is enabled.
What causes this issue? The budget availability control is either active for this cost center or this cost center is assigned to a budget-carrying co...
ESH_HANA_ADMIN240
Could not determine fulltext indices for table &1.&2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
ESH_HANA_ADMIN241
HANA Destination for CDS connectivity is not unique - &1 &2 &3 &4
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.