Message type: E = Error
Message class: FCO_AVC_CC - Availability Control: Cost Centers
Message number: 012
Message text: Chart of accounts hierarchy differs for cost center &1 and profile.
Cost center &V1& references chart of accounts &V2& and the assigned
budget availability control profile, with account hierarchy &V3&,
references chart of accounts &V4&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
You can assign a budget availability control profile to cost center &V1&
, which contains G/L account hierarchy with the chart of account &V2&.
Error message extract from SAP system. Copyright SAP SE.
The SAP error message FCO_AVC_CC012 indicates that there is a mismatch in the chart of accounts hierarchy for a specific cost center and the associated profile. This typically occurs in the context of controlling (CO) and financial accounting (FI) when trying to perform activities that involve cost centers, such as budgeting or planning.
Cause: The error arises due to the following reasons: Different Chart of Accounts: The cost center is assigned to a different chart of accounts than the one defined in the controlling area or the profile being used. Profile Configuration: The profile used for the cost center may not be correctly configured to match the chart of accounts hierarchy. Cost Center Assignment: The cost center may have been created or modified in a way that it no longer aligns with the expected hierarchy for the associated profile.
Solution: To resolve the error, you can take the following steps: Check Cost Center Configuration: Go to the transaction code
Get instant SAP help. Sign up for our Free Essentials Plan.
FCO_AVC_CC011
Cost center &1 references cost center &2, which isn't budget-carrying.
What causes this issue? Cost center &V2& is specified as the budget-carrying cost center for cost center &V1&. However, cost center &...
FCO_AVC_CC010
Cost center &1 doesn't exist. Select an existing cost center.
What causes this issue? Cost center &V1& doesn't exist in controlling area &V2& as of &V3&.System Response The system i...
FCO_AVC_CC013
Tolerance limit of &2% for cost center &1 has been reached in FY &3.
What causes this issue? If you change the cost center, the budget tolerance limit of &V2&% for cost center &V1& in fiscal year &V...
FCO_AVC_CC014
Availability control is active and "Lock Commitment Updates" is enabled.
What causes this issue? The budget availability control is either active for this cost center or this cost center is assigned to a budget-carrying co...