Do you have any question about this error?
Message type: E = Error
Message class: FARR_PROCESS_CHECK - Messages for Input Checks in Process Layer
Message number: 067
Message text: POB &1: Finalization date earlier than start date. This is not supported
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
FARR_PROCESS_CHECK067
- POB &1: Finalization date earlier than start date. This is not supported ?The SAP error message FARR_PROCESS_CHECK067 indicates that there is an issue with the finalization date of a process (in this case, a POB - Project Object Business) being set earlier than the start date. This is not supported because it creates a logical inconsistency in the timeline of the process.
Cause:
The error typically arises due to one of the following reasons:
- Data Entry Error: The finalization date was incorrectly entered as being earlier than the start date.
- System Configuration: There may be a configuration issue in the system that allows for incorrect date entries.
- Data Migration Issues: If data was migrated from another system, it may have brought in incorrect date values.
Solution:
To resolve this error, you can take the following steps:
Check Dates: Review the start and finalization dates in the relevant transaction or document. Ensure that the finalization date is set to a date that is equal to or later than the start date.
Correct the Dates: If you find that the finalization date is indeed earlier than the start date, update the finalization date to a valid date.
Review Configuration: If this issue occurs frequently, review the configuration settings in the SAP system to ensure that there are no rules or settings that might allow for such inconsistencies.
Data Validation: Implement data validation checks in your processes to prevent users from entering invalid date combinations in the future.
Consult Documentation: Refer to SAP documentation or help resources for any specific guidelines related to the POB process and date handling.
Contact Support: If the issue persists or if you are unsure about making changes, consider reaching out to your SAP support team or consulting with an SAP expert.
Related Information:
By following these steps, you should be able to resolve the error and prevent it from occurring in the future.
Get instant SAP help. Start your 7-day free trial now.
FARR_PROCESS_CHECK066
Quantity and Delivered_qty_diff of fulfillment item of POB &1 are empty
What causes this issue? The performance obligation has event type <ZK>PD</>. For this event type, the fields <ZK>Quantity</> ...
FARR_PROCESS_CHECK065
Negative perf. oblig. &1 must not be marked as residual allocation
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
FARR_PROCESS_CHECK068
Performance obligation &1 for cost of acquisition cannot have linked POBs
What causes this issue? The performance obligation for cost of acquisition has a leading role. This is not supported.System Response The system issu...
FARR_PROCESS_CHECK069
Performance obligation &1 for cost of acquisition must be distinct
What causes this issue? The performance obligation for cost of acquisition is non-distinct. This is not supported.System Response The system issues ...
Click on this link to search all SAP messages.