Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 242
Message text: &1 &2: Constraint conflicts with predecessor/successor (&3 &4)
You have either set a start constraint for the task &V1& &V2& and the
constraint date conflicts with the predecessor relationship for &V3&
&V4& or you have set a finish constraint for the task &V1& &V2& and the
constraint date conflicts with the successor relationship for &V3& &V4&.
The start or finish constraint date reduces the lag that is defined
between this task and the corresponding predecessor or successor task.
This is not permitted.
Therefore, there is a <ZH>scheduling conflict</>; the system cannot take
the influence of the relationship into account in scheduling.
The constraint is reduced.
Check the data of the predecessor or successor relationships for &V3&
&V4& and the start or finish constraint for task &V1& &V2&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED242
- &1 &2: Constraint conflicts with predecessor/successor (&3 &4) ?The SAP error message DPR_SHARED242 indicates that there is a constraint conflict in a project or task scheduling scenario. This typically occurs in the context of project management within SAP, particularly when using the SAP Project System (PS) or SAP Portfolio and Project Management (PPM) modules. The error message provides information about the conflicting predecessor or successor relationships between tasks.
Cause: The error message DPR_SHARED242 is triggered when: Constraint Conflicts: There are conflicting constraints set on a task that prevent it from being scheduled correctly in relation to its predecessor or successor tasks. For example, if a task is set to start on a specific date but its predecessor is scheduled to finish later than that date, a conflict arises. Incorrect Task Relationships: The relationships (dependencies) between tasks may not be correctly defined, leading to scheduling issues. Resource Availability: If resources assigned to tasks are not available during the scheduled time, it can also lead
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED241
&1 &2: Calculated finish conflicts with finish constraint
What causes this issue? You have defined a finish constraint on a superior project element. The calculated earliest or latest finish date of the proj...
DPR_SHARED240
&1 &2: Calculated start conflicts with start constraint
What causes this issue? You have defined a start constraint on a superior project element. The calculated earliest or latest start date of the projec...
DPR_SHARED243
&1 &2: Phase overlap was caused by task (&3)
What causes this issue? You define a constraint or set an actual date for a task which calculates the superior phase in such a way that this phase ov...
DPR_SHARED244
&1 &2: Undo constraint; violates time frame of project
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.