How To Fix DPR_SHARED240 - &1 &2: Calculated start conflicts with start constraint


SAP Error Message - Details

  • Message type: E = Error

  • Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

  • Message number: 240

  • Message text: &1 &2: Calculated start conflicts with start constraint

  • Show details Hide details
  • What causes this issue?

    You have defined a start constraint on a superior project element. The
    calculated earliest or latest start date of the project element &V1&
    &V2& violates this constraint.
    Example:
    The start constraint <ZK>Must start on</> is defined with the start
    constraint 4.28. However, the calculated start date of the task is 4.26.

    System Response

    &V1& &V2& does not have any lower-level project elements, for example,
    task without subtasks:
    The system transfers the start date of the constraint from the superior
    project element as the corresponding start date for the project element
    &V1& &V2&.
    &V1& &V2& does have lower-level project elements, for example, task with
    subtasks:
    The system does <ZH>not</> transfer the start date of the constraint
    from the superior project element as the corresponding start date for
    the project element &V1& &V2& because this is defined by the lower-level
    project elements in bottom-up scheduling.

    How to fix this error?

    In <LS>bottom-up scheduling</>, the dates of the superior project
    elements are generally specified by the dates of their lower-level
    project elements.
    Therefore, check the constraint on the superior project element. A
    constraint on one of the lower-level project elements can have the same
    effect.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message DPR_SHARED240 - &1 &2: Calculated start conflicts with start constraint ?

    The SAP error message DPR_SHARED240 indicates that there is a conflict between the calculated start date of a project or task and the start constraint that has been defined for it. This typically occurs in the context of project management within SAP, particularly when using the Project System (PS) or Portfolio and Project Management (PPM) modules.

    Cause:

    1. Start Constraint: The project or task has a defined start constraint (e.g., "Must Start On," "Start No Earlier Than," etc.) that is not being met by the calculated start date.
    2. Dependencies: There may be dependencies or relationships with other tasks that affect the start date.
    3. Resource Availability: Resource constraints or availability issues may lead to a calculated start date that conflicts with the defined constraints.
    4. Scheduling Settings: The scheduling settings or parameters may not align with the constraints set for the project or task.

    Solution:

    1. Review Constraints: Check the start constraints defined for the project or task. Ensure that they are set correctly and that they align with the intended project timeline.
    2. Adjust Dates: If the calculated start date is incorrect, you may need to adjust the project or task dates manually to resolve the conflict.
    3. Check Dependencies: Review any predecessor or successor relationships that may be influencing the start date. Adjust these relationships if necessary.
    4. Resource Allocation: Ensure that the resources required for the task are available. If not, consider reallocating resources or adjusting the project schedule.
    5. Recalculate Schedule: After making adjustments, recalculate the project schedule to see if the conflict is resolved.
    6. Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing constraints and scheduling in your version of SAP.

    Related Information:

    • Transaction Codes: You may use transaction codes like CJ20N (Project Builder) or CJ02 (Change Project) to review and modify project details.
    • SAP Notes: Check for any relevant SAP Notes that may address known issues or provide additional guidance on this error message.
    • User Forums: Consider visiting SAP community forums or user groups for insights from other users who may have encountered similar issues.

    By following these steps, you should be able to identify the cause of the error and implement a solution to resolve it.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant