Do you have any question about this error?
Message type: E = Error
Message class: DPR_CALC - cProjects Costing Integration
Message number: 011
Message text: Maintain a cost element for cost/revenue rate &1
The system could not find a cost element for the cost/revenue rate &V1&
for the organization &V2&.
Costing can not determine planned costs due to the missing cost
element.
Enter a cost element in Customizing under <ls>Integration with Other
mySAP.com Components</> --> <ls>Collaboration Projects</> -->
<ls>Accounting Integration</> --> <DS:SIMG.CPR_FINR3_KOSERSZUOG>Assign
Cost Elements and Activity Types</> .
Define the cost element for the organization &V2&, for a superior
organization, or without any reference to an organization.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_CALC011
- Maintain a cost element for cost/revenue rate &1 ?The SAP error message DPR_CALC011, which states "Maintain a cost element for cost/revenue rate &1," typically occurs in the context of project management and cost planning within the SAP system, particularly in the Project System (PS) or the Project Management (PM) module. This error indicates that a cost element has not been defined for a specific cost or revenue rate that is being referenced in a project.
Cause:
The error is usually caused by one of the following reasons:
- Missing Cost Element: The cost element associated with the specified cost/revenue rate has not been maintained in the system.
- Incorrect Configuration: The configuration settings for the project or the cost/revenue rate may not be set up correctly.
- Data Inconsistency: There may be inconsistencies in the data related to the project or the cost elements.
Solution:
To resolve the error, you can follow these steps:
Check Cost Element Configuration:
- Go to the transaction code KA01 (Create Cost Element) or KA02 (Change Cost Element) in SAP.
- Verify if the cost element for the specified cost/revenue rate exists. If it does not, you will need to create it.
Maintain Cost Element for the Rate:
- Navigate to the relevant configuration settings for the project or cost/revenue rate.
- Ensure that a valid cost element is assigned to the cost/revenue rate in question.
Review Project Settings:
- Check the project settings in transaction CJ20N (Project Builder) or CJ02 (Change Project).
- Ensure that all necessary cost elements are properly assigned to the project.
Consult Documentation:
- Review the SAP documentation or help files related to cost elements and project management to ensure that you are following the correct procedures.
Test Changes:
- After making the necessary changes, test the functionality again to ensure that the error no longer occurs.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in project management and controlling within SAP.
Get instant SAP help. Start your 7-day free trial now.
DPR_CALC010
Maintain a revenue element for cost/revenue rate &1
What causes this issue? The system cannot find a revenue element for the cost/revenue rate &V1& for the organization &V2&.System Resp...
DPR_CALC009
Maintain an activity type for cost/revenue rate &1
What causes this issue? The system cannot find an activity type for the cost/revenue rate &V1& for the organization &V2&.System Respo...
DPR_CALC012
Internal order &1 for the project &2 is currently locked
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_CALC013
Internal order &1 for the project &2 could not be saved
What causes this issue? The system issues an error message and will not allow you to continue with this transaction until the error is resolved. Syst...
Click on this link to search all SAP messages.