Do you have any question about this error?
Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 757
Message text: Order & operation &: Dispatching/rescheduling was not carried out
You have tried to dispatch/reschedule operations. In the strategy
profile you have activated <ls>Insert operation</> or <ls>Close
gaps</>.
Since one of the operations selected could not be dispatched or
rescheduled the system has not dispatched or rescheduled any of the
operations.
Check whether there is still enough remaining available capacity at the
work center.
Try to dispatch a smaller number of operations at the same time.
When dispatching or rescheduling do without the functions <ls>Insert
operation</> and <ls>Close gaps</>.
Error message extract from SAP system. Copyright SAP SE.
CY757
- Order & operation &: Dispatching/rescheduling was not carried out ?The SAP error message CY757 ("Order & operation &: Dispatching/rescheduling was not carried out") typically occurs in the context of production planning and control within the SAP system. This error indicates that the system was unable to dispatch or reschedule a specific order or operation due to certain conditions not being met.
Causes:
- Capacity Constraints: The work center may not have enough capacity available to accommodate the order or operation.
- Missing Master Data: Required master data such as routing, work center, or production version may be incomplete or incorrect.
- Order Status: The order may be in a status that does not allow for dispatching or rescheduling (e.g., "TECO" - Technically Completed).
- Scheduling Parameters: Incorrect scheduling parameters or settings in the production order may prevent the operation from being dispatched.
- Dependencies: There may be dependencies or constraints related to other orders or operations that prevent the dispatching of the current order.
Solutions:
- Check Capacity: Review the capacity of the work center to ensure that it can handle the additional load. You may need to adjust the capacity or reschedule other orders.
- Review Master Data: Ensure that all relevant master data (routing, work center, production version) is correctly set up and complete.
- Order Status: Check the status of the order. If it is in a status that does not allow dispatching, you may need to change the status or take appropriate actions to enable dispatching.
- Adjust Scheduling Parameters: Review and adjust the scheduling parameters in the production order to ensure they are set correctly.
- Check Dependencies: Investigate any dependencies or constraints that may be affecting the order and resolve them accordingly.
Related Information:
If the problem persists after checking these areas, it may be beneficial to consult with your SAP support team or refer to SAP documentation for further troubleshooting steps.
Get instant SAP help. Start your 7-day free trial now.
CY756
Order & operation & have already been dispatched
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CY755
Order & operation &: Deallocation not permitted because of status
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CY758
Availability check for order & could not be carried out.
What causes this issue? A possible cause is a database error.How to fix this error? You should contact your system administrator.Error message extra...
CY759
Order & has missing materials
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.