Do you have any question about this error?
Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 010
Message text: Number & for capacity requirements & lies in the critical area
Almost all of the numbers in the number range have been used.
Increase the number range interval or create a new number range for the
order type &V2&. To do this contact your system administrator.
Error message extract from SAP system. Copyright SAP SE.
CY010
- Number & for capacity requirements & lies in the critical area ?The SAP error message CY010 typically indicates an issue related to capacity requirements in production planning. Specifically, it suggests that there is a problem with the capacity of a work center or resource that is critical for the production process. Here’s a breakdown of the cause, potential solutions, and related information for this error:
Cause:
- Capacity Overload: The work center or resource is overloaded with more capacity requirements than it can handle within the specified time frame.
- Incorrect Capacity Planning: The capacity planning settings for the work center may not be configured correctly, leading to discrepancies in available capacity versus required capacity.
- Scheduling Conflicts: There may be scheduling conflicts due to overlapping production orders or maintenance activities that are not accounted for.
- Resource Availability: The resources (machines, labor, etc.) may not be available due to maintenance, breakdowns, or other operational issues.
Solution:
Review Capacity Planning:
- Check the capacity settings for the affected work center. Ensure that the available capacity is correctly defined in the system.
- Adjust the capacity planning parameters if necessary.
Analyze Production Orders:
- Review the production orders scheduled for the work center. Identify any orders that may be causing the overload and consider rescheduling or adjusting their quantities.
Check for Conflicts:
- Look for any scheduling conflicts that may be causing the capacity to be overstated. This includes checking for maintenance schedules or other production orders that may overlap.
Adjust Production Schedule:
- If the work center is indeed overloaded, consider redistributing the workload to other work centers or adjusting the production schedule to alleviate the pressure.
Increase Capacity:
- If feasible, consider increasing the capacity of the work center by adding shifts, resources, or optimizing the production process.
Consult with Production Planning Team:
- Collaborate with the production planning team to understand the broader implications of the capacity issues and to develop a long-term solution.
Related Information:
CM01
(Capacity Planning) or CM21
(Capacity Leveling) to analyze and adjust capacity requirements.CR01
to ensure that all parameters are set correctly.C223
(Capacity Evaluation) to get insights into capacity utilization and requirements.By following these steps, you should be able to identify the root cause of the CY010 error and implement a solution to resolve the capacity requirements issue.
Get instant SAP help. Start your 7-day free trial now.
CY009
Error when assigning a number to the capacity requirements
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CY006
Incorrect date format
What causes this issue? When the system tried to find the date format for an input/output field, an error occurred.System Response The system issues...
CY011
Assign highest number & for capacity requirement &
What causes this issue? The last number (&V1&) has been assigned in the number range allocated.How to fix this error? Increase the number ra...
CY015
Error when inserting in table &1: Of &2 records &3 records were posted
What causes this issue? An internal error occurred when inserting an entry in table &V1&. Out of &V2& records &V3& records we...
Click on this link to search all SAP messages.