Message type: E = Error
Message class: CRM_LEASING_CHANGE - Messages for Changes to Leases
Message number: 126
Message text: The exercise date does not correspond to the old lease start date
This exercise date is not possible at item level for change process
&V1&, because it does not correspond to the start date of the old
financing item.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Enter the start date of the old financing item as the exercise date for
this process.
Error message extract from SAP system. Copyright SAP SE.
CRM_LEASING_CHANGE126
- The exercise date does not correspond to the old lease start date ?The SAP error message CRM_LEASING_CHANGE126 indicates that there is a mismatch between the exercise date and the old lease start date in the leasing contract. This error typically occurs when you are trying to change or exercise an option in a leasing contract, and the system detects that the dates do not align as expected.
Cause:
- Date Mismatch: The exercise date you are trying to enter does not match the original lease start date or is not within the valid range of dates for the lease.
- Incorrect Data Entry: The exercise date may have been entered incorrectly, or there may be a misunderstanding of the lease terms.
- Configuration Issues: There may be configuration settings in the leasing module that are not set up correctly, leading to this validation error.
Solution:
- Verify Dates: Check the exercise date you are trying to enter and ensure it corresponds to the old lease start date. The exercise date should typically be on or after the lease start date.
- Review Lease Terms: Look at the terms of the lease agreement to ensure that the exercise date is valid and permissible according to the contract.
- Correct Data Entry: If the exercise date was entered incorrectly, correct it and try again.
- Consult Documentation: Review the SAP documentation or help files related to leasing contracts to understand the expected date relationships.
- Configuration Check: If you suspect a configuration issue, consult with your SAP administrator or a consultant who specializes in the leasing module to ensure that all settings are correct.
- Testing: If changes are made, test the scenario in a development or test environment before applying changes in production.
Related Information:
If the issue persists after following these steps, it may be beneficial to reach out to SAP support or your internal IT team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
CRM_LEASING_CHANGE125
Enter a different exercise date; see long text
What causes this issue? This exercise date is not possible at item level for change process number &V1&, because it does not agree with the b...
CRM_LEASING_CHANGE124
Enter a different exercise date; see long text
What causes this issue? This exercise date is not possible at header level for change process &V1&, because it does not agree with the billin...
CRM_LEASING_CHANGE127
The exercise date does not correspond to the old EOL date
What causes this issue? This exercise date is not possible at item level for change process &V1& because it does not correspond to the end da...
CRM_LEASING_CHANGE128
The execution date is earlier than the old lease start date
What causes this issue? You entered an exercise date at item level for change process &V1& that is earlier than the start date of the old fin...
Click on this link to search all SAP messages.