Message type: E = Error
Message class: CP - Task list messages: Core data
Message number: 898
Message text: Not all changes passed on to update program
A COMMIT WORK has been invoked, despite the fact that not all routing
changes were passed on to the update program.
Because the COMMIT WORK removes all locks, these changes cannot later be
posted. This may lead to inconsistencies.
The system is unable to decide what is to be done with these changes.
Processing is discontinued.
Pass on all changes made to routings to the update program before
invoking COMMIT WORK. To do this, you can use the function module
EAM_TASKLIST_POST for example.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
CP898
- Not all changes passed on to update program ?The SAP error message CP898 ("Not all changes passed on to update program") typically occurs in the context of the SAP Change and Transport System (CTS) or during the transport of changes between different SAP systems. This error indicates that there was an issue with the transport request, and not all changes were successfully processed or passed on to the update program.
Causes:
- Incomplete Transport Request: The transport request may not have included all the necessary objects or changes.
- Lock Issues: There may be locks on the objects being transported, preventing the update program from processing them.
- Dependencies: There could be dependencies on other objects or transport requests that have not been included or processed.
- Configuration Issues: There may be configuration issues in the transport management system.
- Errors in the Update Program: The update program itself may have encountered errors while processing the changes.
Solutions:
- Check Transport Request: Review the transport request to ensure that all necessary objects and changes are included. You can do this by using transaction code SE09 or SE10.
- Release and Re-import: If the transport request is incomplete, you may need to release it again and re-import it into the target system.
- Check Locks: Use transaction SM12 to check for any locks on the objects being transported. If locks are found, you may need to release them.
- Review Dependencies: Ensure that all dependent objects are included in the transport request. You may need to create additional transport requests for these dependencies.
- Check Logs: Review the transport logs for any specific error messages or warnings that can provide more context on what went wrong. You can check the logs using transaction SLG1.
- Consult Basis Team: If the issue persists, it may be necessary to consult your SAP Basis team for further investigation and resolution.
Related Information:
By following these steps, you should be able to identify the cause of the CP898 error and implement a solution to resolve it.
Get instant SAP help. Sign up for our Free Essentials Plan.
CP897
Program error: Code & during update of file &.
What causes this issue? Internal error: errors occured in file & while changing records.How to fix this error? INCLUDE NA_SYSAD1Error message ex...
CP896
Program error: Code & when inserting file &.
What causes this issue? Internal error: errors occurred in file & while inserting records aufgetreten.How to fix this error? INCLUDE NA_SYSAD1Er...
CP899
Maintain tables via Customizing
What causes this issue? You do not have the authorization to maintain the table using Transaction SM31. Only SAP programmers should have the authori...
CP900
Key date in the future is not allowed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.