Do you have any question about this error?
Message type: E = Error
Message class: CP - Task list messages: Core data
Message number: 478
Message text: Plants in header and sub-operation have different controlling areas
You selected a work center for a sub-operation which belongs to a
different company code as the routing header.
You can use work centers from different plants in your routing. You
can assign plants from all company codes.
However, a company code check is set up in your system for the fiscal
year.
Choose a work center from the same company code as the routing header.
Error message extract from SAP system. Copyright SAP SE.
CP478
- Plants in header and sub-operation have different controlling areas ?The SAP error message CP478 indicates that there is a mismatch between the controlling areas of the plant specified in the header and the sub-operation of a production order or a similar document. This typically occurs in the context of production planning and controlling (PP/CO) modules when trying to create or process a production order, routing, or similar objects.
Cause:
- Different Controlling Areas: The primary cause of this error is that the plant defined in the header of the production order is assigned to a different controlling area than the plant defined in the sub-operation.
- Configuration Issues: There may be configuration issues in the system where the plants are not correctly assigned to the same controlling area.
- Data Entry Errors: Incorrect data entry while creating or modifying the production order or routing can lead to this error.
Solution:
Check Plant Assignments:
- Verify the controlling area assignments for both the header plant and the sub-operation plant. You can do this by navigating to the configuration settings in SAP.
- Use transaction codes like
SPRO
to access the configuration settings and check the assignment of plants to controlling areas.Correct the Production Order:
- If you find that the plants are assigned to different controlling areas, you will need to either change the plant in the header or the sub-operation to ensure they are consistent.
- You can do this by editing the production order or routing in the relevant transaction (e.g.,
CO02
for production orders).Review Routing and BOM:
- If the issue is related to a routing or bill of materials (BOM), ensure that all components and operations are assigned to the correct plant and controlling area.
Consult with Configuration Team:
- If you are unsure about the correct configuration or if changes are needed, consult with your SAP configuration team or a functional consultant who specializes in PP/CO.
Testing:
- After making the necessary changes, test the process again to ensure that the error is resolved.
Related Information:
CO01
(Create Production Order), CO02
(Change Production Order), CO03
(Display Production Order), and C223
(Maintain Routing).By following these steps, you should be able to resolve the CP478 error and ensure that your production orders are correctly configured within the SAP system.
Get instant SAP help. Start your 7-day free trial now.
CP477
Plants in header and operation have different company codes
What causes this issue? You have selected a work center for an operation which belongs to a different controlling area as the routing header. You can...
CP476
The plants in header and operation have different company codes.
What causes this issue? You selected a work center for the operation which belongs to a different company code as the routing header. You can use wor...
CP479
Plants in header and sub-operation have different controlling areas
What causes this issue? You selected a work center for the sub-operation which belongs to a different company code as the routing header. You can use...
CP480
---------- Operations: work center ----------------------------
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.