Do you have any question about this error?
Message type: E = Error
Message class: COTU - Messages for Partial Conversion Planned Order -> Prod. Order
Message number: 013
Message text: Contract quantity in sub-network is zero
You want to convert a multi-level planned order into a
<GL:collective_order>collective order</>. The quantities from the
subordinate planned orders are converted in the proportion of partial
quantity to planned order quantity. This proportion is on one level so
small that the order quantity becomes zero after rounding.
The conversion of the multi-level planned order is terminated.
You should check the partial quantity specified.
Error message extract from SAP system. Copyright SAP SE.
COTU013
- Contract quantity in sub-network is zero ?The SAP error message COTU013, which states "Contract quantity in sub-network is zero," typically occurs in the context of project systems or network management within SAP. This error indicates that there is an issue with the contract quantity associated with a specific sub-network in a project or order.
Cause:
- Zero Contract Quantity: The most direct cause of this error is that the contract quantity for the specified sub-network has been set to zero. This can happen if the contract was not properly defined or if there was an error in data entry.
- Missing or Incorrect Assignment: The sub-network may not be correctly assigned to a contract, or the contract itself may not have been created or activated.
- Data Inconsistencies: There may be inconsistencies in the data related to the project, network, or contract that lead to this error.
- Configuration Issues: There could be configuration issues in the project system or network management settings that prevent the contract quantity from being recognized.
Solution:
- Check Contract Quantity: Verify the contract quantity for the sub-network in question. Ensure that it is greater than zero and that the contract is correctly defined.
- Review Assignments: Ensure that the sub-network is correctly assigned to the appropriate contract. Check the assignment settings in the project or network management module.
- Data Validation: Validate the data related to the project, network, and contract. Look for any discrepancies or missing information that could be causing the issue.
- Recreate or Adjust Contract: If the contract is missing or incorrectly set up, consider recreating it or adjusting the existing contract to ensure it has the correct quantities and assignments.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing contracts and networks within your version of SAP.
- Contact Support: If the issue persists after checking the above points, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.
Related Information:
By following these steps, you should be able to identify and resolve the cause of the COTU013 error in your SAP system.
Get instant SAP help. Start your 7-day free trial now.
COTU012
It is not possible to enter additional partial quantities
What causes this issue? You want to enter further partial quantities. The partial quantities already entered reach or exceed the open quantity of the...
COTU011
Indicator 'Delete planned order' is set
What causes this issue? The sum of the partial quantities has reached or exceeded the open quantity of the planned order. The system has set the indi...
COTU014
Production order &2 was generated from planned order &1
What causes this issue? From planned order &V1& a partial quantity has been converted to production order &V2&.System Response The s...
COTU015
Quantity of zero for generated order is not possible
What causes this issue? You have set a partial quantity to zero. However, a production order has already been generated for this partial quantity. A ...