Message type: E = Error
Message class: COCMN - Order Change Management - Network-Specific Messages
Message number: 102
Message text: Activity & in network & has been partially confirmed
In the change profile &V3& it was specified that the status
<ZH>partially released</> for operation &V1& in network &V2& represents
a conflict for the change step.
INCLUDE OCM_SYSTEM_RESPONSE OBJECT DOKU ID TX LANGUAGE EN
INCLUDE OCM_WHAT_TO_DO OBJECT DOKU ID TX LANGUAGE EN
Error message extract from SAP system. Copyright SAP SE.
COCMN102
- Activity & in network & has been partially confirmed ?The SAP error message COCMN102, which states "Activity & in network & has been partially confirmed," typically occurs in the context of project management and production planning within SAP. This message indicates that an activity in a network (such as a project network or production order) has been partially confirmed, meaning that some of the planned work has been completed, but not all of it.
Cause:
- Partial Confirmation: The most common cause of this error is that the activity has been confirmed for a portion of the planned work, but there are still remaining quantities or durations that need to be confirmed.
- Incorrect Confirmation Process: The user may have attempted to confirm the activity without completing all necessary steps or without the required permissions.
- Status of the Activity: The activity may be in a status that does not allow for further confirmations or changes.
- Dependencies: There may be dependencies or constraints related to the activity that prevent it from being fully confirmed.
Solution:
- Check Confirmation Status: Review the confirmation status of the activity in the network. You can do this by navigating to the relevant transaction (e.g., CATS, CO11N) and checking the confirmation details.
- Complete Remaining Work: If there is remaining work that needs to be confirmed, ensure that it is completed and then proceed to confirm the remaining quantities or durations.
- Review Activity Settings: Check the settings of the activity in the network to ensure that it is configured correctly for confirmations. This includes checking the status and any dependencies.
- Use Correct Transaction: Make sure you are using the correct transaction for confirming the activity. For example, use CO11N for confirming production orders or CATS for time confirmations.
- Consult Documentation: If you are unsure about the confirmation process, refer to SAP documentation or user manuals for guidance on how to properly confirm activities in networks.
Related Information:
By following these steps, you should be able to resolve the COCMN102 error and successfully confirm the activity in the network.
Get instant SAP help. Sign up for our Free Essentials Plan.
COCMN101
Activity & in network & has been released
What causes this issue? In the change profile &V3& it was specified that the status <ZH>released</> for operation &V1& in...
COCMN100
* Messages from feasabiltiy checks for synchronization steps *
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
COCMN103
Activity & in network & has been confirmed
What causes this issue? In the change profile &V3& it was specified that the status <ZH>confirmed</> for operation &V1& i...
COCMN106
Activity or activity element & already exists in network &
What causes this issue? The change step should be used to insert the operation/operation element &V1& in the network &V2&. However, a...
Click on this link to search all SAP messages.