Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 708
Message text: No relationships to superior activity & must be created
Activity &V1& is superior to your subnetwork.
It does not have any relationships.
Error message extract from SAP system. Copyright SAP SE.
CN708
- No relationships to superior activity & must be created ?The SAP error message CN708 ("No relationships to superior activity & must be created") typically occurs in the context of project management and network planning within SAP. This error indicates that a subordinate activity does not have a defined relationship with its superior (or predecessor) activity, which is necessary for proper scheduling and planning.
Cause:
Missing Relationships: The primary cause of this error is that the subordinate activity (the one you are trying to create or modify) does not have any defined relationships (dependencies) with its superior activity. In project management, activities often depend on one another, and these dependencies must be explicitly defined in the system.
Incorrect Activity Status: The status of the activities may not allow for the creation of relationships. For example, if an activity is marked as completed or has a status that prevents changes, you may encounter this error.
Data Entry Errors: There may be data entry errors or inconsistencies in the project structure that lead to this issue.
Solution:
Create Relationships: To resolve the error, you need to create the necessary relationships between the subordinate activity and its superior activity. This can typically be done in the project planning screen:
- Navigate to the activity in question.
- Use the "Relationships" tab or section to define the required relationships (e.g., Finish-to-Start, Start-to-Start, etc.) with the superior activity.
Check Activity Status: Ensure that both the superior and subordinate activities are in a status that allows for relationship creation. If an activity is completed or locked, you may need to change its status.
Review Project Structure: Check the overall project structure to ensure that all activities are correctly defined and that there are no missing links or inconsistencies.
Use Transaction Codes: You can use transaction codes like
CJ20N
(Project Builder) orCN21
(Create Network) to manage and review the project activities and their relationships.Consult Documentation: If you are unsure about the relationships needed, consult the project documentation or guidelines that outline the dependencies between activities.
Related Information:
CJ20N
, CN21
, CN22
, and CN24
for managing project activities and networks.If the issue persists after trying the above solutions, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in project systems.
Get instant SAP help. Start your 7-day free trial now.
CN707
A purchase order already exists for purchase requisition &1 &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN706
Purchase requisition for material & cannot be generated
What causes this issue? The system tries to automatically generate a purchase requistion for an externally procured component. This occurs in the fol...
CN709
Material & is marked for deletion (check)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN710
Maintain both indicator and date for constraint
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.