Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 683
Message text: Purchasing data for component &1, activity &2 is incomplete
You want to release an activity. You have allocated one or more
externally procured material components to the activity. Important data
for purchasing was missing at the time of release, such as:
G/L account
Purchasing group
Material group
The activity is not released.
Check and complete the purchasing data for the material components.
Release the activity again.
Error message extract from SAP system. Copyright SAP SE.
CN683
- Purchasing data for component &1, activity &2 is incomplete ?The SAP error message CN683 indicates that there is incomplete purchasing data for a specific component and activity in a project. This error typically arises in the context of project management and controlling, particularly when dealing with project-related purchasing information.
Cause:
The error message CN683 can occur due to several reasons, including:
Missing Purchasing Information: The purchasing data for the specified component (material) and activity (work breakdown structure element) is not fully maintained. This could include missing details such as vendor information, purchasing group, or purchasing organization.
Incomplete Master Data: The material master or vendor master data may not be properly set up, leading to incomplete purchasing information.
Project Structure Issues: The project structure may not be correctly defined, or the component may not be assigned to the correct project or activity.
Configuration Issues: There may be configuration settings in the system that are not aligned with the requirements for purchasing data.
Solution:
To resolve the CN683 error, you can take the following steps:
Check Purchasing Data:
- Navigate to the relevant component in the project and check the purchasing data.
- Ensure that all required fields are filled out, including vendor, purchasing group, and purchasing organization.
Review Material Master:
- Go to the material master record for the component and verify that all necessary purchasing information is maintained.
- Ensure that the material is assigned to the correct purchasing organization.
Verify Vendor Master:
- Check the vendor master data to ensure that it is complete and correctly linked to the purchasing data for the component.
Project Structure Review:
- Review the project structure to ensure that the component is correctly assigned to the appropriate work breakdown structure (WBS) element and activity.
Configuration Check:
- If necessary, consult with your SAP configuration team to ensure that the system settings are correctly configured for project purchasing.
Use Transaction Codes:
- Use transaction codes like
ME23N
(Display Purchase Order),MM03
(Display Material), andMK03
(Display Vendor) to check the relevant data.Related Information:
CJ20N
(Project Builder) for project management.By following these steps, you should be able to identify and correct the issues causing the CN683 error in your SAP system.
Get instant SAP help. Start your 7-day free trial now.
CN682
Release date item &1 activity &2 is &3 days in the past
What causes this issue? You have triggered the creation of a purchase requisition. The system determines the release date as the difference between t...
CN681
Requirements date of item & is in the past
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN684
Activity & was not released -> see log
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN685
Network & was not released -> see log
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.