Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 624
Message text: Standard network contains loops and cannot be scheduled
The standard network cannot be scheduled because the relationships to
activities have created a loop.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
RESET N1
Call up the network structure graphic.
Select the menu options <LS>Edit -> Functions -> Loop analysis ->
Execute</>.
The relationships causing the loop are highlighted.
Choose new relationships between activities so the loop no longer
exists.
Select the menu options <LS>Edit -> Functions -> Loop analysis ->
Execute</>.
The relationships are no longer highlighted.
Error message extract from SAP system. Copyright SAP SE.
CN624
- Standard network contains loops and cannot be scheduled ?The SAP error message CN624 indicates that there are loops in the standard network of a project, which prevents the scheduling of the project. This error typically arises in the context of project management within SAP, particularly when using the Project System (PS) module.
Cause:
The primary cause of the CN624 error is the presence of circular dependencies in the network activities. This can happen due to:
- Incorrect Activity Relationships: Activities may be incorrectly linked, creating a situation where an activity depends on itself, either directly or indirectly.
- Missing or Incorrectly Defined Milestones: If milestones are not properly defined or linked, it can lead to circular dependencies.
- Manual Changes: Manual adjustments to the network structure that inadvertently create loops.
Solution:
To resolve the CN624 error, follow these steps:
Check Activity Relationships:
- Go to the network in question and review the relationships between activities.
- Ensure that there are no circular dependencies. Each activity should have a clear predecessor and successor.
Use the Network Overview:
- Utilize the network overview (transaction code
CN21
orCN22
) to visualize the network structure.- Look for any activities that point back to themselves or create a loop.
Adjust Relationships:
- If you find any incorrect relationships, adjust them to eliminate the loops.
- Ensure that the logical flow of the project is maintained.
Check for Milestones:
- Verify that all milestones are correctly defined and do not create circular dependencies with the activities.
Re-schedule the Network:
- After making the necessary adjustments, attempt to re-schedule the network using transaction code
CN41
orCN42
.Use the Scheduling Check:
- Use the scheduling check functionality to identify any remaining issues in the network.
Related Information:
CN21
: Create NetworkCN22
: Change NetworkCN41
: Schedule NetworkCN42
: Display NetworkBy following these steps, you should be able to identify and resolve the cause of the CN624 error, allowing you to successfully schedule your project network in SAP.
Get instant SAP help. Start your 7-day free trial now.
CN623
Standard network contains & loop(s)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN622
Standard network contains more than the nine loops found
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN625
You do not have authorization for plant &1, usage &2 and planner group &3
What causes this issue? You want to create a standard network alternative.System Response You do not have the necessary authorization for the plant,...
CN628
Standard network contains no relationships
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.