Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 061
Message text: Project definitions have different header and activity
The network you are editing has account assignment.
The WBS element that you want to assign to an activity has a different
project definition than the one you have entered in the network header.
The WBS element in the activity must have the same project definition as
in the network header.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
RESET N1
Check to make sure that you entered the correct WBS element. If
necessary change your entry.
Check the project definition of the WBS element and change it if
necessary.
Error message extract from SAP system. Copyright SAP SE.
CN061
- Project definitions have different header and activity ?The SAP error message CN061 ("Project definitions have different header and activity") typically occurs in the context of project management within SAP, particularly when dealing with project definitions and their associated activities. This error indicates that there is a mismatch between the project header and the activities that are linked to it.
Cause:
- Mismatch in Project Definition: The project header and the activities may belong to different project definitions. This can happen if activities are incorrectly assigned to a project or if there are inconsistencies in the project structure.
- Incorrect Assignment: Activities may have been assigned to a different project or have been created under a different project definition than intended.
- Data Integrity Issues: There may be data integrity issues in the database, such as corruption or incorrect entries that lead to mismatched project definitions.
Solution:
- Check Project Assignment: Verify that the activities are correctly assigned to the intended project definition. You can do this by navigating to the project structure and checking the hierarchy.
- Reassign Activities: If you find that activities are incorrectly assigned, you may need to reassign them to the correct project definition. This can typically be done in the project management module.
- Review Project Structure: Ensure that the project structure is correctly defined and that all activities are linked to the correct project header.
- Use Transaction Codes: Utilize transaction codes like
CJ20N
(Project Builder) to review and modify project definitions and their associated activities.- Check for Data Consistency: Run consistency checks or reports to identify any discrepancies in project definitions and activities. This can help in identifying any underlying data issues.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on project management and error resolution.
Related Information:
CJ01
(Create Work Breakdown Structure), CJ02
(Change Work Breakdown Structure), and CJ20N
(Project Builder).By following these steps, you should be able to identify the cause of the CN061 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
CN060
Cost display could not be generated due to missing parameters
What causes this issue? The cost display could not be created. An internal error occurred.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG'...
CN059
Network has no costs
What causes this issue? No planned costs could be calculated for the activity.Error message extract from SAP system. Copyright SAP SE. ...
CN062
& Finish date is in the past
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN063
You cannot create a subnetwork
What causes this issue? You have not maintained all the parameters in Customizing which are necessary to create a subnetwork.System Response INCLUDE...
Click on this link to search all SAP messages.