Message type: E = Error
Message class: CMS_CAG - Message Class for Collateral Agreement
Message number: 241
Message text: Valid to date of portion&1 must be earlier than agreement valid to date
There could be two possibilities:
The valid-to date of the collateral agreement portion &V1& is later than
the valid-to date of the parent collateral agreement.
You have not maintained the valid-to date of the parent collateral
agreement.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Enter a valid-to date of the collateral agreement portion on or before
the valid-to date of the parent collateral agreement.
Error message extract from SAP system. Copyright SAP SE.
CMS_CAG241
- Valid to date of portion&1 must be earlier than agreement valid to date ?The SAP error message CMS_CAG241 indicates that there is a validation issue with the dates in a contract or agreement. Specifically, the error states that the "Valid to date" of a portion (likely a specific part of a contract or agreement) must be earlier than the "Valid to date" of the overall agreement. This is a common issue in contract management where the validity periods of different components must be logically consistent.
Cause:
- Date Configuration: The "Valid to date" of a specific portion of the agreement is set to a date that is equal to or later than the "Valid to date" of the overall agreement.
- Data Entry Error: During the creation or modification of the contract or agreement, incorrect dates may have been entered.
- System Configuration: There may be a configuration issue in the SAP system that is not enforcing the date validation correctly.
Solution:
- Check Dates: Review the "Valid to date" of both the portion and the overall agreement. Ensure that the portion's date is set to a date that is earlier than the agreement's date.
- Modify Dates: If the portion's date is incorrect, update it to a valid date that meets the requirement.
- Validation Logic: If you are a system administrator or have access to configuration settings, check the validation logic in the system to ensure it is functioning correctly.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing contract dates and resolving related errors.
Related Information:
If the issue persists after checking and correcting the dates, consider reaching out to your SAP support team for further assistance.
Get instant SAP help. Sign up for our Free Essentials Plan.
CMS_CAG240
Valid from date of portion&1 must be later than agreement valid from date
What causes this issue? There could be two possibilities: The valid-from date of the collateral agreement portion is earlier than the valid-from date...
CMS_CAG239
Enter the date until which collateral agreement portion &1 is valid
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CMS_CAG242
Collateral agreement portion &1 validity dates have been updated
What causes this issue? If you do not maintain the validity dates for the collateral agreement portions, then collateral agreement dates are automati...
CMS_CAG243
Agreement validity dates must be same or later than the agreement date
What causes this issue? The <ZK>valid-from</> and <ZK>valid-to</> dates of the collateral agreement must be later than the da...
Click on this link to search all SAP messages.