Do you have any question about this error?
Stop googling SAP errors. Use our Free Essentials plan instead - no credit card needed. Start Now →
Message type: E = Error
Message class: CKBK - Messages of the Valuation Functions
Message number: 006
Message text: Valuation of &1 not successful with primary cost component split
The
<DS:GLOS.3526B5F2AFAB52B9E10000009B38F974>primary cost component split
</> of the internal activity or business process &v1& does not
correspond to the price.
The primary cost component splt is ignored, and valuation proceeds
using the price.
If necessary, execute
<DS:GLOS.3526B67CAFAB52B9E10000009B38F974>price calculation</>.
<DS:TRAN.KSPI>Execute Price Calculation</>
Error message extract from SAP system. Copyright SAP SE.
CKBK006
- Valuation of &1 not successful with primary cost component split ?The SAP error message CKBK006 indicates that there was an issue with the valuation of a cost object (like a cost center, internal order, or project) when using the primary cost component split. This error typically arises during the execution of a transaction that involves cost allocation or cost assessment, particularly when the system is trying to split costs into their respective components.
Cause:
- Missing Configuration: The primary cost component split may not be properly configured in the system. This includes missing settings in the controlling area or cost element master data.
- Inconsistent Data: There may be inconsistencies in the data related to the cost components, such as missing or incorrect cost element assignments.
- Cost Component Structure: The cost component structure may not be defined correctly or may not match the requirements of the transaction being executed.
- Cost Element Issues: The cost elements used in the transaction may not be set up for primary cost component splitting.
- Missing Master Data: Required master data (like cost centers, internal orders, etc.) may be missing or incorrectly maintained.
Solution:
- Check Configuration: Verify the configuration of the primary cost component split in the controlling area. Ensure that the cost component structure is defined and assigned correctly.
- Review Cost Elements: Check the cost elements involved in the transaction to ensure they are set up for primary cost component splitting. You can do this by reviewing the cost element master data.
- Validate Master Data: Ensure that all relevant master data (cost centers, internal orders, etc.) is correctly maintained and that there are no missing entries.
- Analyze Transaction Data: Look at the specific transaction that triggered the error to identify any inconsistencies or missing data.
- Use Transaction Codes: Utilize transaction codes like KSB1 (Cost Centers: Actual Line Items) or KOB1 (Orders: Actual Line Items) to analyze the cost postings and identify any discrepancies.
- Consult Documentation: Refer to SAP documentation or help resources for detailed guidance on configuring primary cost component splits.
Related Information:
By following these steps, you should be able to identify the root cause of the CKBK006 error and implement the necessary solutions to resolve it.
Get instant SAP help. Sign up for our Free Essentials Plan.
CKBK005
&1 overhead on sales order item with overhead structure &2
&cause& <ls>&V1&. Overhead Application</> In a <DS:GLOS.3526B6D1AFAB52B9E10000009B38F974>sales order cost estimate&...
CKBK004
Material/plant: &1/&2, overhead structure &3
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CKBK007
Business area is blank
What causes this issue? <DS:GLOS.3526B73AAFAB52B9E10000009B38F974>Partner version</> &V1& includes the <DS:GLOS.3526B86CAFAB52...
CKBK008
No valid source of supply could be determined for material &
What causes this issue? No valid source of supply could be found for material &v1& in plant &v2&.System Response The material is not...
Click on this link to search all SAP messages.