How To Fix CK075 - Planning date is in the past -> cost estimate cannot be saved


CK075 - Overview

  • Message type: E = Error

  • Message class: CK - Product Costing Messages

  • Message number: 075

  • Message text: Planning date is in the past -> cost estimate cannot be saved

  • Show details Hide details
  • What causes this issue?

    The date you specified for the costing run is in the past. However, the
    <DS:GLOS.costing_type>costing type</> in the costing variant is for the
    <DS:GLOS.standard_cost_estimate>standard cost estimate</>.
    Because the standard cost estimate serves to calculate <ZH>future</>
    prices, it does not make sense to carry out the costing run with a date
    in the past.

    System Response

    If you use a date in the past, then
    you can carry out the costing run in <ZH>online</> mode, but the system
    cannot save the costing results
    you cannot carry out the costing run either in the <ZH>background</> or
    with <ZH>parallel processing</>

    How to fix this error?

    Create a costing run with a date that is not in the past.
    Use a different costing variant if necessary.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CK075 - Planning date is in the past -> cost estimate cannot be saved ?
    The SAP error message CK075 ("Planning date is in the past -> cost estimate cannot be saved") typically occurs when you are trying to save a cost estimate in the SAP system, but the planning date you have entered is earlier than the current date. This is a validation check to ensure that cost estimates are not created for dates that have already passed, as it could lead to inconsistencies in financial reporting and planning.
    
    Cause: Planning Date: The planning date you specified for the cost estimate is set to a date that is earlier than the current system date. System Settings: The system may have specific settings or configurations that prevent saving cost estimates with past planning dates.
    Solution: To resolve this error, you can take the following steps: Check the Planning Date: Review the planning date you have entered in the cost estimate. Ensure that it is set to today’s date or a future

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.