Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 559
Message text: Activity start earlier than WBS element & start date
The start date that you entered for the activity is earlier than the
start date of the WBS element.
You cannot adjust the dates from top to bottom.
Enter a start date for the activity that is later or the same as the
the start date for the WBS element.
Error message extract from SAP system. Copyright SAP SE.
CJ559
- Activity start earlier than WBS element & start date ?The SAP error message CJ559 indicates that an activity's start date is earlier than the start date of the associated Work Breakdown Structure (WBS) element. This typically occurs in project management scenarios within SAP, particularly when dealing with project planning and scheduling.
Cause:
- Date Mismatch: The start date of the activity is set before the start date of the WBS element. This can happen if the activity is created or modified without considering the constraints of the WBS element.
- Incorrect Planning: The project planning might not have been aligned properly, leading to discrepancies in the scheduling of activities and WBS elements.
- Changes in Project Structure: If the WBS element's dates were changed after the activity was created, it could lead to this error.
Solution:
- Adjust Activity Start Date: Change the start date of the activity to be on or after the start date of the WBS element. This can be done in the activity details within the project management module.
- Review WBS Dates: Check the start date of the WBS element to ensure it is set correctly. If necessary, adjust the WBS element's start date to accommodate the activity's schedule.
- Re-evaluate Project Plan: Review the overall project plan to ensure that all activities and WBS elements are aligned in terms of dates. This may involve adjusting multiple activities or WBS elements.
- Use Project Planning Tools: Utilize SAP's project planning tools to visualize the project timeline and make necessary adjustments to avoid such conflicts.
Related Information:
By addressing the date discrepancies and ensuring proper alignment between activities and WBS elements, you can resolve the CJ559 error and maintain a coherent project schedule.
Get instant SAP help. Start your 7-day free trial now.
CJ558
Field length exceeded when calculating project & duration
What causes this issue? An internal error has occurred while calculating the duration of project definition &V1&.System Response The field w...
CJ557
No activities exist for WBS element &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ560
Activity finish later than WBS element & finish date
What causes this issue? The finish date that you entered for the activity is later than the finish date for the WBS element.System Response You cann...
CJ561
WBS element & has activities. Delete activities first
What causes this issue? You can only delete the dates in a WBS element if there aren't any activities assigned to the WBS element anymore.System...
Click on this link to search all SAP messages.