How To Fix CJ561 - WBS element & has activities. Delete activities first


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CJ - Project master data and structure

  • Message number: 561

  • Message text: WBS element & has activities. Delete activities first

  • Show details Hide details
  • What causes this issue?

    You can only delete the dates in a WBS element if there aren't any
    activities assigned to the WBS element anymore.

    System Response

    INCLUDE 'NA_ALLG_NOFUNCTION' OBJECT DOKU ID TX

    How to fix this error?

    You have the following options in deleting the dates in the WBS elements

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CJ561 - WBS element & has activities. Delete activities first ?

    The SAP error message CJ561 indicates that you are trying to delete a Work Breakdown Structure (WBS) element that still has associated activities. In SAP Project System (PS), a WBS element can only be deleted if it does not have any linked activities, as these activities are part of the project structure and must be managed before the WBS element can be removed.

    Cause:

    The error occurs because:

    • The WBS element you are attempting to delete has one or more activities (e.g., network activities, tasks) associated with it.
    • SAP enforces this rule to maintain the integrity of project data and ensure that all project activities are accounted for.

    Solution:

    To resolve this error, you need to follow these steps:

    1. Identify Associated Activities:

      • Use transaction code CJ20N (Project Builder) or CJ03 (Display WBS) to view the WBS element and identify the activities linked to it.
    2. Delete or Change Activities:

      • If you want to delete the WBS element, you must first delete all associated activities. You can do this by:
        • Navigating to the activities in the Project Builder and deleting them individually.
        • If there are multiple activities, you may need to delete them in bulk or use a mass change transaction if available.
    3. Check for Dependencies:

      • Ensure that there are no dependencies or relationships that might prevent the deletion of the activities. You may need to adjust or remove any dependencies before proceeding.
    4. Delete the WBS Element:

      • Once all activities are deleted, you can return to the WBS element and attempt to delete it again.

    Related Information:

    • Transaction Codes:

      • CJ20N: Project Builder
      • CJ03: Display WBS
      • CJ02: Change WBS
      • CJ01: Create WBS
    • Documentation:

      • Refer to SAP Help documentation for Project System for detailed information on managing WBS elements and activities.
    • Best Practices:

      • Always back up your project data before making deletions.
      • Consider the impact of deleting activities and WBS elements on project reporting and financials.

    By following these steps, you should be able to resolve the CJ561 error and successfully delete the WBS element.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant