Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 542
Message text: New start date is later than the old one
You can only enter an earlier start date.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Error message extract from SAP system. Copyright SAP SE.
CJ542
- New start date is later than the old one ?The SAP error message CJ542 ("New start date is later than the old one") typically occurs in the context of project management within SAP, particularly when dealing with project definitions, work breakdown structures (WBS), or network activities. This error indicates that you are trying to change the start date of a project or activity to a date that is later than its current start date, which is not allowed in SAP.
Cause:
- Date Change Attempt: You are attempting to change the start date of a project or activity to a date that is later than the existing start date.
- Dependencies: There may be dependencies or constraints set on the project or activity that prevent the start date from being moved forward.
- Project Structure: The project structure may have been defined in such a way that changing the start date violates the logical sequence of tasks.
Solution:
To resolve the CJ542 error, you can take the following steps:
Check Current Dates: Review the current start date of the project or activity. Ensure that the new start date you are trying to set is earlier than the existing start date.
Adjust Dates: If you need to change the start date, ensure that the new date is earlier than the current date. If you need to push the project back, you may need to adjust other related dates accordingly.
Review Dependencies: Check for any dependencies or constraints that may be affecting the start date. You may need to adjust these dependencies to allow for the desired date change.
Consult Project Management Guidelines: Ensure that any changes you are making comply with your organization's project management guidelines and practices.
Use Transaction Codes: If you are using transaction codes like CJ20N (Project Builder) or CJ02 (Change Project), ensure you are following the correct procedures for changing project dates.
Seek Help from SAP Support: If you are unable to resolve the issue, consider reaching out to your SAP support team or consulting the SAP Help Portal for further assistance.
Related Information:
By following these steps, you should be able to resolve the CJ542 error and successfully manage your project dates in SAP.
Get instant SAP help. Start your 7-day free trial now.
CJ541
WBS element & must be an account assignment element
What causes this issue? The activity or activities that you want to assign to a WBS element, are in a network with an account assignment. The WBS ele...
CJ540
No network assignment entered for WBS element &
What causes this issue? When you enter dates in time scheduling, the system creates a network with these dates in the background. You must enter how ...
CJ543
No date changes exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ544
Network type "&" does not exist
What causes this issue? Network type &V1& either: does not exist or was not entered in the network profile In either case, you cannot create ...
Click on this link to search all SAP messages.