Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 497
Message text: Several sets of dates selected: You cannot insert a time bar
You have selected several sets of dates. You must select only one set
of dates, for example, basic dates, to be able to insert a new time
bar.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
Select the set of dates you want using the menu options <LS>Settings ->
Set of dates</>.
Error message extract from SAP system. Copyright SAP SE.
CJ497
- Several sets of dates selected: You cannot insert a time bar ?The SAP error message CJ497 ("Several sets of dates selected: You cannot insert a time bar") typically occurs in the context of project management within SAP, particularly when dealing with project structures, dates, and scheduling.
Cause: This error arises when you attempt to insert a time bar (a graphical representation of time periods) in a project that has multiple sets of dates selected. This can happen if: You have selected multiple activities or elements in a project that have different start and end dates. The system does not allow the insertion of a time bar because it cannot determine a single time frame that applies to all selected elements.
Solution: To resolve this error, you can try the following steps: Deselect Activities: Ensure that you only have one activity or project element selected when trying to insert the time bar. If you need to visualize multiple activities, consider doing them one at a time. Check Date Consistency: Verify
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ496
You cannot insert lines in the table area
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ495
WBS element & has no finish date. Scheduling not possible.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ498
There are no relationships which can be displayed.
What causes this issue? You have either not shown all activities or the activities you have displayed, do not have relationshipsSystem Response INCL...
CJ499
No graphic profile with index & exists
What causes this issue? The graphics profile which you entered for the project planning board profile does not have the index &V1&.System Res...