Do you have any question about this error?
Stop Googling SAP errors. Use our Free Essentials plan instead - instant AI help, no credit card needed. Start Now →
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 152
Message text: Reconcile the milestone date with that of the WBS element
You entered a date for the milestone which is not within the date
interval of the WBS element &V1& to which the milestone is assigned:
Start,,&V2&
Finish,,&V3&
Correct the dates for the milestone or the WBS element &V1&.
Error message extract from SAP system. Copyright SAP SE.
CJ152
- Reconcile the milestone date with that of the WBS element ?The SAP error message CJ152, which states "Reconcile the milestone date with that of the WBS element," typically occurs in the context of project management within SAP, particularly when dealing with Work Breakdown Structures (WBS) and milestones.
Cause:
This error arises when there is a discrepancy between the milestone date defined in the project and the corresponding WBS element date. The system expects that the milestone date should align with the dates set for the WBS element. Common causes include:
- Date Mismatch: The milestone date is set earlier or later than the planned start or finish date of the WBS element.
- Changes in Project Plan: If the project plan has been modified (e.g., dates have been changed), the milestone dates may not have been updated accordingly.
- Incorrect Configuration: There may be configuration issues in the project management settings that lead to this inconsistency.
Solution:
To resolve the CJ152 error, you can follow these steps:
Check Milestone Dates: Go to the project definition and check the milestone dates. Ensure that they are correctly set according to the project timeline.
Review WBS Element Dates: Navigate to the WBS element associated with the milestone and verify its planned start and finish dates. Make sure they align with the milestone dates.
Adjust Dates: If there is a discrepancy, adjust either the milestone date or the WBS element dates to ensure they are consistent. You can do this in the project management transaction (e.g., CJ02 for changing WBS elements).
Recheck Dependencies: If the milestone is dependent on other tasks or milestones, ensure that all related dates are synchronized.
Consult Project Documentation: Review any project documentation or change logs to understand why the dates may have been altered and ensure that all stakeholders are aware of the changes.
Use Transaction Codes: Utilize relevant transaction codes such as CJ20N (Project Builder) or CJ02 (Change WBS Element) to make the necessary adjustments.
Related Information:
By following these steps, you should be able to resolve the CJ152 error and ensure that your project milestones and WBS elements are properly aligned.
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ151
No confirmations for WBS element "&" exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ150
No dates set. Scheduling could not be carried out
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ153
Select a valid line
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ154
There are still activities in the buffer
What causes this issue? You have copied or cut activities which are still in the buffer.How to fix this error? The system issues an error message an...
Click on this link to search all SAP messages.