Message type: E = Error
Message class: CI_DRAFTPRD_MESSAGE -
Message number: 052
Message text: Planned delivery time is 0 for externally procured product
You are creating a master record for a product that is to be procured
externally. However, you have not entered a planned delivery time.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
A planned delivery time of zero only makes sense if the product can beCheck your screen and field values
Error message extract from SAP system. Copyright SAP SE.
CI_DRAFTPRD_MESSAGE052
- Planned delivery time is 0 for externally procured product ?The SAP error message CI_DRAFTPRD_MESSAGE052 indicates that there is an issue with the planned delivery time for an externally procured product. Specifically, it means that the planned delivery time is set to 0, which is not valid for products that are procured externally. Here’s a breakdown of the cause, potential solutions, and related information:
Cause:
- Configuration Issue: The planned delivery time for the material in question has not been set or has been incorrectly set to 0 in the material master data.
- Material Master Data: The material master record for the externally procured product may not have the necessary data filled in, particularly in the purchasing view.
- Vendor Information: The vendor associated with the product may not have the correct lead time information configured.
- Procurement Type: The procurement type for the material may not be set correctly, leading to the system not recognizing the need for a planned delivery time.
Solution:
Check Material Master Data:
- Go to the material master record (transaction code MM03).
- Check the purchasing view and ensure that the planned delivery time is set to a valid value (greater than 0).
- If it is set to 0, update it to a realistic planned delivery time based on your procurement process.
Review Vendor Master Data:
- Check the vendor master data (transaction code XK03 or MK03).
- Ensure that the lead time and other relevant procurement details are correctly maintained.
Adjust Procurement Type:
- Verify the procurement type for the material in the material master. Ensure it is set to "External procurement" if that is the intended method of procurement.
Check Purchase Info Records:
- If applicable, check the purchase info records (transaction code ME13) for the material and vendor combination to ensure that the planned delivery time is correctly maintained.
Consult with Business Process Owners:
- If you are unsure about the appropriate planned delivery time, consult with the relevant business process owners or procurement team to determine the correct value.
Related Information:
By following these steps, you should be able to resolve the error message CI_DRAFTPRD_MESSAGE052 and ensure that the planned delivery time is set correctly for your externally procured products.
Get instant SAP help. Start your 7-day free trial now.
CI_DRAFTPRD_MESSAGE051
You have maintained Revision Level. Specify a Change Number as well.
What causes this issue? You wanted to display data for the product's revision level. However, this product does not have a revision level yet.Sy...
CI_DRAFTPRD_MESSAGE050
Enter a product number
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CI_DRAFTPRD_MESSAGE053
In-house production time is 0 for product produced in-house
What causes this issue? You are creating a master record for a product that is to be produced in-house. However, you have not entered an in-house pro...
CI_DRAFTPRD_MESSAGE054
Lot size (products planning) & is not defined
What causes this issue? The value you have entered is not defined in the system. The system issues an error message and will not allow you to continu...
Click on this link to search all SAP messages.