Message type: E = Error
Message class: CACSIB - Commissions: Interface and Pending Case Processing
Message number: 402
Message text: Contract number & is not maintained in PD-Org
The commission contract &V1& is referenced in the participation for the
commission case. This contract is not known in the commission system.
The commission case is categorized as pending. If it was possible to
create a commission document in spite of this error (for further
participants, for example) the account assignment for the missing
contract is also missing.
Correct the commission contract number via processing of cases pending
or create the commission contract and release the commission case for
further processing.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
CACSIB402
- Contract number & is not maintained in PD-Org ?The SAP error message CACSIB402 indicates that a specific contract number is not maintained in the relevant organizational unit (PD-Org) within the SAP system. This error typically arises in the context of contract management or when dealing with contract-related transactions in SAP Customer Activity Repository (CAR) or SAP Convergent Charging (SAP CC).
Cause:
- Missing Configuration: The contract number you are trying to access or process is not linked to the relevant organizational unit in the system.
- Data Inconsistency: There may be inconsistencies in the data where the contract is not properly assigned to the PD-Org.
- Incorrect Input: The contract number entered may be incorrect or does not exist in the system.
Solution:
Check Contract Assignment:
- Verify that the contract number is correctly assigned to the relevant PD-Org. You can do this by navigating to the contract management area in SAP and checking the organizational assignments.
Maintain Contract in PD-Org:
- If the contract is not assigned, you will need to maintain the contract in the relevant PD-Org. This can typically be done through the configuration settings in the SAP system.
- Use transaction codes like
CACS_CONTRACT
or similar to access the contract management area and make the necessary assignments.Data Consistency Check:
- Run data consistency checks to ensure that all contracts are properly linked to their respective organizational units. This may involve using specific reports or tools within SAP.
Consult Documentation:
- Refer to SAP documentation or help files for detailed steps on how to maintain contracts and organizational assignments.
Contact Support:
- If you are unable to resolve the issue, consider reaching out to your SAP support team or consulting with SAP support for further assistance.
Related Information:
CACS_CONTRACT
, CACS_CONTRACTS
, or others specific to your SAP version.By following these steps, you should be able to identify the cause of the error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
CACSIB401
No evaluation path maintained for application &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CACSIB400
*** Processing participation *******************************************
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CACSIB403
Contract & was not assigned at &: &
What causes this issue? Commission contract &V1& was referred to in the commission case participation. This contract is not assigned to any p...
CACSIB404
Position & not assigned to any organizational unit
What causes this issue? In commission case participation, reference was made to commission contract &V1&. This contract is not assigned to an...