Do you have any question about this error?
Message type: E = Error
Message class: BQ - Messages for Budgeting and Planning
Message number: 190
Message text: Payments for the full release are less than the cumulated release.
The overall release in the payment budget for one or more funds
centers/ commitment items is less than the cumulative release.
The cumulative release is the total of all the annual releases.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Check your input.
Error message extract from SAP system. Copyright SAP SE.
BQ190
- Payments for the full release are less than the cumulated release. ?The SAP error message BQ190, which states "Payments for the full release are less than the cumulated release," typically occurs in the context of payment processing in SAP, particularly when dealing with budget management and release strategies. This error indicates that the total payments made or planned for a particular budget release are less than the total amount that has been released for that budget.
Cause:
Budget Release Issues: The error often arises when the total payments (actual or planned) do not match the total budget that has been released. This can happen if:
- There are discrepancies in the budget release amounts.
- Payments have been recorded incorrectly or not at all.
- There are changes in the budget that have not been reflected in the payment processing.
Configuration Errors: Incorrect configuration in the budget management settings or release strategies can also lead to this error.
Data Entry Errors: Manual entry errors in the payment documents or budget release documents can cause mismatches.
Solution:
To resolve the BQ190 error, you can take the following steps:
Check Budget Releases:
- Review the budget release documents to ensure that the amounts released are correct and match the intended budget.
Verify Payments:
- Check the payment documents to ensure that all payments have been recorded correctly and that they correspond to the released budget amounts.
Adjust Budget or Payments:
- If there are discrepancies, you may need to adjust either the budget release amounts or the payment amounts to ensure they align.
Review Configuration:
- If the issue persists, review the configuration settings related to budget management and release strategies in SAP. Ensure that they are set up correctly according to your organization's policies.
Consult Documentation:
- Refer to SAP documentation or help resources for specific guidance on budget management and payment processing.
Seek Help from SAP Support:
- If you are unable to resolve the issue, consider reaching out to SAP support or your internal SAP team for further assistance.
Related Information:
By following these steps, you should be able to identify the cause of the BQ190 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
BQ179
- &: & <& (&)
What causes this issue? The annual release in payment budget &V2& &V4& for funds center/ commitment item &V1& is less than di...
BQ178
Annual release for payments & less than distributed release
What causes this issue? The annual release in the payment budget for one or more funds centers/ commitment items is less than the distributed release...
BQ191
- &: & <& (&)
What causes this issue? The overall release payment budget &V2& &V4& for funds center/commitment item &V1& is less than cumul...
BQ192
Payments for the total budget are less than the full release
What causes this issue? The overall values in the payment budget for one or more funds centers/commitment items are less than the overall release.Sys...