Do you have any question about this error?
Message type: E = Error
Message class: BQ - Messages for Budgeting and Planning
Message number: 111
Message text: - &: & <& (&)
The distributable commitment budget (annual values) is insufficient to
execute the desired action.
This may have the following causes:
You are trying to enter more commitment budget in a subordinate budget
structure element than is actually available in the superordinate
budget structure element.
You are trying to reduce commitment budget in a superordinate budget
structure element.
The system will not execute the action.
The annual budget for commitments for funds center/commitment item &V1&
is &V2& &V4&, the distributed value is &V3& &V4&.
Reduce the amount entered so that it does not exceed the distributable
value of &V2& &V4&.
Error message extract from SAP system. Copyright SAP SE.
BQ111
- - &: & <& (&) ?The SAP error message BQ111 typically relates to issues with the business partner (BP) data in the SAP system. This error can occur in various contexts, such as during the creation or modification of business partner records, and it usually indicates that there is a problem with the data being entered or processed.
Cause:
- Missing Required Fields: The error may arise if mandatory fields in the business partner data are not filled out correctly.
- Data Format Issues: The data entered may not conform to the expected format (e.g., incorrect date formats, invalid characters).
- Inconsistent Data: There may be inconsistencies in the data that violate business rules or constraints defined in the system.
- Authorization Issues: The user may not have the necessary permissions to create or modify the business partner data.
- Configuration Issues: There may be configuration settings in the SAP system that are not aligned with the data being processed.
Solution:
- Check Required Fields: Ensure that all mandatory fields are filled out correctly. Review the business partner data for any missing information.
- Validate Data Formats: Make sure that the data entered adheres to the required formats. For example, check date formats, numeric fields, and any other specific formatting rules.
- Review Business Rules: Check for any business rules or constraints that may be causing the error. Ensure that the data being entered complies with these rules.
- User Authorizations: Verify that the user has the necessary authorizations to perform the action. If not, contact your SAP administrator to adjust the permissions.
- Consult Configuration Settings: If the issue persists, consult with your SAP configuration team to review the settings related to business partner data.
Related Information:
BP
(Business Partner) to access the business partner master data and check for issues.If the problem persists after following these steps, it may be beneficial to reach out to SAP support or your internal SAP team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
BQ110
- &: & <& (&)
What causes this issue? The distributable commitment budget (overall values) is insufficient to execute the desired action. This may have the followi...
BQ106
- &: & <& (&)
What causes this issue? The total budget &V2& &V4& in order &V1& is less than the cumulative budget &V3& &V4&...
BQ112
- &: & <& (&)
What causes this issue? The overall budget for commitments &V2& &V4& in funds center/commitment item &V1& is less than cumula...
BQ113
Commitments (overall budget) less than distributed budget
What causes this issue? The commitment budget overall values for one or more funds centers/ commitment items are less than the distributed budget.Sys...
Click on this link to search all SAP messages.