How To Fix BQ016 - Overall budget less than distributed budget


SAP Error Message - Details

  • Message type: E = Error

  • Message class: BQ - Messages for Budgeting and Planning

  • Message number: 016

  • Message text: Overall budget less than distributed budget

  • Show details Hide details
  • What causes this issue?

    The overall budget for one or more funds center(s)/commitment item(s)
    less than the distributed budget.

    System Response

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    How to fix this error?


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message BQ016 - Overall budget less than distributed budget ?

    The SAP error message BQ016 ("Overall budget less than distributed budget") typically occurs in the context of budget management within SAP, particularly when working with budgetary control in the Public Sector or in projects. This error indicates that the total budget allocated for a particular cost center, project, or internal order is less than the amount that has already been distributed or committed against that budget.

    Cause:

    1. Budget Allocation Issues: The overall budget for a project or cost center has not been set correctly or is insufficient to cover the distributed amounts.
    2. Incorrect Budget Distribution: There may have been an error in how the budget was distributed across various line items or cost centers.
    3. Changes in Budget: If the budget was reduced after commitments were made, this could lead to the error.
    4. Posting Errors: Incorrect postings or entries that exceed the available budget can trigger this message.

    Solution:

    1. Review Budget Allocation: Check the overall budget assigned to the relevant cost center, project, or internal order. Ensure that it is sufficient to cover all distributed amounts.
    2. Adjust Budget: If the overall budget is indeed less than the distributed budget, consider increasing the budget allocation to accommodate the distributed amounts.
    3. Check Commitments: Review the commitments and postings made against the budget. Ensure that they are accurate and reflect the intended budget distribution.
    4. Reallocate Budget: If necessary, reallocate the budget to ensure that it aligns with the distributed amounts.
    5. Consult with Finance Team: If you are unsure about how to proceed, consult with your finance or budgeting team for guidance on how to adjust the budget appropriately.

    Related Information:

    • Transaction Codes: You may use transaction codes like S_ALR_87013558 (Budget/Actual/Commitment) or S_ALR_87013542 (Budget Overview) to analyze budget data.
    • Budget Control Settings: Review the settings in the budget control configuration to ensure they align with your organization's policies and procedures.
    • Documentation: Refer to SAP documentation or help resources for detailed guidance on budget management and error resolution.
    • User Roles: Ensure that you have the appropriate authorizations to make changes to budget allocations or to view budget-related reports.

    By following these steps, you should be able to identify the cause of the BQ016 error and implement a solution to resolve it.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker