Message type: E = Error
Message class: BJ - Standard WBS
Message number: 017
Message text: Project & is not allocated to a standard WBS.
Your project, &V1&, was not created from a standard project.
You can only assign a network to a project when it also was created
with this standard WBS.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
RESET N1
Using "possible entries" select a project that was created with this
standard WBS and then select <PF>copy</>.
Using <PF>Create project</> create a new project from the standard WBS.
Error message extract from SAP system. Copyright SAP SE.
BJ017
- Project & is not allocated to a standard WBS. ?The SAP error message BJ017 indicates that a project is not allocated to a standard Work Breakdown Structure (WBS) element. This error typically arises when you are trying to perform an action related to a project that requires it to be linked to a valid WBS element, but the system cannot find the necessary association.
Cause: Missing WBS Assignment: The project you are working with has not been assigned to a standard WBS element. Incorrect Project Structure: The project structure may not be correctly defined, or the project may not be set up properly in the system. Project Type: The project type may not allow for a standard WBS assignment.
Configuration Issues: There may be configuration issues in the project management settings that prevent the assignment of a WBS element.
Solution: Check Project Assignment: Go to the project definition in SAP and verify if it is assigned to a WBS element. If it is not assigned, you can assign
Get instant SAP help. Sign up for our Free Essentials Plan.
BJ016
Project & is allocated to standard WBS &.
What causes this issue? Your project &V1& was created with the standard WBS &V2&. In this situation, you cannot assign a network to t...
BJ011
Standard WBS & does not exist.
What causes this issue? Standard WBS "&V1&" does not exist.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ...
BJ018
Another standard WBS is used for this material
What causes this issue? The material for this sales order has been assigned to project &v1& with the standard WBS &v2&. You have now ...
BJ021
Standard WBS element & does not exist.
What causes this issue? Standard WBS element &V1& does not exist.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID T...
Click on this link to search all SAP messages.