Do you have any question about this error?
Message type: E = Error
Message class: AO_PLANNING - Message Class for Project WGRS-4B4R6S
Message number: 022
Message text: Transfer of plan values not possible due to different object currency
Appropriation request &v1& has a different object currency (&v2&) than
order &v3& (&v4&).
Transferring plan values is possible only if the object currencies of
the appropriation request and the order are the same.
The plan values are not transferred.
Ensure that the order has the same object currency as the appropriation
request. Then repeat the tranfer of plan values.
Error message extract from SAP system. Copyright SAP SE.
AO_PLANNING022
- Transfer of plan values not possible due to different object currency ?The SAP error message AO_PLANNING022 indicates that there is an issue with transferring planning values due to a mismatch in the currency of the objects involved. This typically occurs in the context of SAP's planning and budgeting functionalities, particularly in the context of the SAP Analytics Cloud (SAC) or SAP Business Planning and Consolidation (BPC).
Cause:
The error arises when you attempt to transfer planning values between objects (such as cost centers, profit centers, or other planning entities) that are denominated in different currencies. This can happen in scenarios where:
- Different Currencies: The source and target objects have different currencies assigned to them.
- Currency Conversion Issues: There may be issues with currency conversion settings or rates that prevent the transfer from being processed.
- Configuration Issues: The planning configuration may not allow for cross-currency transfers.
Solution:
To resolve the AO_PLANNING022 error, you can take the following steps:
Check Object Currencies:
- Verify the currencies assigned to the source and target planning objects. Ensure that they are the same or that the system is configured to handle different currencies.
Currency Conversion Settings:
- Review the currency conversion settings in your planning application. Ensure that the necessary exchange rates are maintained and that the system can convert between the currencies involved.
Planning Configuration:
- Check the planning configuration settings in your SAP system. Ensure that the planning area allows for the transfer of values between different currencies if that is intended.
Use Consistent Currencies:
- If possible, standardize the currencies used in your planning objects to avoid such issues in the future.
Consult Documentation:
- Refer to SAP documentation or help resources for specific guidance on handling currency-related issues in your version of SAP.
Contact Support:
- If the issue persists after checking the above points, consider reaching out to SAP support for further assistance. They may provide insights specific to your system configuration.
Related Information:
By following these steps, you should be able to identify and resolve the cause of the AO_PLANNING022 error in your SAP environment.
Get instant SAP help. Start your 7-day free trial now.
AO_PLANNING021
Transfer of plan values not possible due to different object currency
What causes this issue? Appropriation request &v1& has a different object currency (&v2&) than WBS element &v3& (&v4&...
AO_PLANNING020
Net present value cannot be calculated in object currency &2
What causes this issue? The system determines the net present value in object currency &V2& internally by translating controlling area curren...
AO_PLANNING023
Different object currency on order &3 - plan value transfer not possible
What causes this issue? Order &v3& has object currency &v4& and appropriation request &v1& has object currency &v2&.S...
AO_PLANNING024
Transfer of plan vals not possible - different object currency on WBS &3
What causes this issue? WBS element &v3& has object currency &v4& and appropriation request &v1& has object currency &v2&...
Click on this link to search all SAP messages.