Message type: E = Error
Message class: AO - Appropriation requests - Master data / Customizing
Message number: 259
Message text: Transfer of plan values not possible - there are more than 2 measures
You want to transfer plan values to a measure.
However, there are more than two measures assigned to this
appropriation request.
Plan values are not transferred.
Maintain the plan values of the measure in dialog mode.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
AO259
- Transfer of plan values not possible - there are more than 2 measures ?The SAP error message AO259, which states "Transfer of plan values not possible - there are more than 2 measures," typically occurs in the context of planning and budgeting within SAP's Integrated Business Planning (IBP) or SAP Analytics Cloud (SAC) environments. This error indicates that the system is unable to transfer planning values because there are more than two measures involved in the planning process.
Cause: Multiple Measures: The primary cause of this error is that the planning operation you are trying to execute involves more than two measures. In many planning scenarios, SAP restricts the transfer of plan values to a maximum of two measures to maintain data integrity and ensure that the planning process is manageable.
Configuration Issues: There may be configuration settings in the planning area or data model that do not support the transfer of multiple measures. Data Model Limitations: The underlying data model may not be designed to handle
Get instant SAP help. Sign up for our Free Essentials Plan.
AO258
No plan values exist for combined costs or revenue
What causes this issue? There are no plan values for combined costs, nor are there plan values for revenue. Therefore, the system cannot calculate pr...
AO257
You cannot use approp. request type &1 without a project profile
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
AO260
Release is not possible since there is no measure - check
What causes this issue? You want to release appropriation request &V1&. However, there are no measures assigned to appropriation request &...
AO261
Project definition &2 is being processed by user &1
What causes this issue? Project definition &V2& is blocked by user &V1&. Therefore, appropriation request &V2&, which belongs...
Click on this link to search all SAP messages.