Do you have any question about this error?
Message type: E = Error
Message class: AO - Appropriation requests - Master data / Customizing
Message number: 242
Message text: Release is not allowed, since appropriation request &1 is not released
You want to release &V2& &V3&.
However, measure &V2& &V3& is assigned to appropriation request &V1&.
The appropriation request does not allow release of the measure.
Measure &V2& &V3& is not released.
Check the assignment of measure &V2& &V3& to appropriation request &V1&
.
Releasing the measure is only possible if appropriation request &V1& is
released, or if the measure was assigned to appropriation request &V1&
as a preliminary project and the appropriation request has 'created'
status.
Error message extract from SAP system. Copyright SAP SE.
AO242
- Release is not allowed, since appropriation request &1 is not released ?The SAP error message AO242 indicates that a release is not allowed for a specific appropriation request because it has not been released yet. This typically occurs in the context of budget management or project management within SAP, particularly when dealing with investment measures or appropriations.
Cause:
The error occurs when you attempt to perform an action (like posting a transaction or releasing a budget) on an appropriation request that is still in a draft or unapproved state. The appropriation request must be released before any further actions can be taken.
Solution:
To resolve this error, you need to ensure that the appropriation request is properly released. Here are the steps you can follow:
Check the Status of the Appropriation Request:
- Navigate to the transaction where you can view the appropriation request (e.g., transaction code
CJ20N
for project management).- Verify the status of the appropriation request. It should be in a "Released" state.
Release the Appropriation Request:
- If the appropriation request is not released, you will need to release it. This can typically be done through the transaction code
CJ02
(Change Project) orCJ30
(Change Appropriation Request).- Find the appropriation request in question and change its status to "Released."
Check for Required Approvals:
- Ensure that all necessary approvals have been obtained for the appropriation request. Sometimes, there may be workflow processes that need to be completed before a request can be released.
Re-attempt the Action:
- Once the appropriation request is released, you can re-attempt the action that triggered the error message.
Related Information:
Transaction Codes:
CJ20N
: Project BuilderCJ02
: Change ProjectCJ30
: Change Appropriation RequestCJ31
: Display Appropriation RequestAuthorization:
Documentation:
Support:
By following these steps, you should be able to resolve the AO242 error and proceed with your intended actions in SAP.
Get instant SAP help. Start your 7-day free trial now.
AO241
Limited validation, since the system is not set to 'production' status.
What causes this issue? You want to delete the appropriation request. The system status for appropriation requests is set to legacy data transfer or ...
AO240
To delete the approp. request, use the 'save' function
What causes this issue? You chose the transaction for physically deleting an appropriation request. Along with master data screens, the system also o...
AO243
You do not have authorization for copying the variant assignments --->
What causes this issue? You want to copy or assign data to the new version &V1& approval year &V2& of program type &V3&. You ...
AO244
No preinvestment analysis figures are newly calculated
What causes this issue? You chose the 'calculate preinvestment figures' function. You then terminated this function.System Response The sy...
Click on this link to search all SAP messages.