Do you have any question about this error?
Message type: E = Error
Message class: AO - Appropriation requests - Master data / Customizing
Message number: 192
Message text: Maintain the responsible company code for 'create WBS element'
You selected the function 'create WBS element' from the appropriation
request. However, you have not yet maintained the responsible company
code in the appropriation request (under 'organizational units'). The
responsible company code is the company code that is responsible for
carrying out the measure (WBS element).
The WBS element cannot be created from appropriation request &V1&
without a responsible company code.
Enter the responsible company code.
&NOTE&
Note that the system uses the responsible company code, not the
requesting company code, for creating the WBS element.
Error message extract from SAP system. Copyright SAP SE.
AO192
- Maintain the responsible company code for 'create WBS element' ?The SAP error message AO192, which states "Maintain the responsible company code for 'create WBS element'," typically occurs when you are trying to create a Work Breakdown Structure (WBS) element in SAP Project System (PS) without having a responsible company code assigned to the project or WBS element.
Cause:
- Missing Company Code Assignment: The project or WBS element you are trying to create does not have a responsible company code assigned. This is a mandatory field in the project definition.
- Configuration Issues: There may be configuration issues in the Project System settings that prevent the assignment of a company code.
- Authorization Issues: The user may not have the necessary authorizations to create or modify the project or WBS element.
Solution:
Assign a Company Code:
- Navigate to the project definition or the WBS element you are trying to create.
- Ensure that a responsible company code is assigned. You can do this by going to the project definition (transaction code
CJ20N
orCJ01
) and checking the "Company Code" field.- If it is not assigned, you can enter the appropriate company code.
Check Project Profile:
- Ensure that the project profile assigned to the project allows for the assignment of a company code. You can check this in the project profile settings.
Configuration Check:
- If you have access, check the configuration settings in the Project System (transaction code
SPRO
). Navigate to:Project System -> Structures -> Work Breakdown Structure -> Define Project Profile
- Ensure that the settings are correctly configured to allow for company code assignment.
Authorization Check:
- Verify that the user has the necessary authorizations to create or modify WBS elements. This can be checked with your SAP security team.
Consult Documentation:
- If the issue persists, consult the SAP documentation or reach out to your SAP support team for further assistance.
Related Information:
CJ01
- Create Work Breakdown StructureCJ20N
- Project BuilderSPRO
- Customizing Implementation GuideBy following these steps, you should be able to resolve the AO192 error and successfully create the WBS element in SAP.
Get instant SAP help. Start your 7-day free trial now.
AO191
WBS element &1 will be created when you save
What causes this issue? You selected the function 'create WBS element.' The system created WBS element &V1& and assigned it to the ...
AO190
Approp. request &1 does not have any measures - no replacement made -->
What causes this issue? You want to set the status 'replaced by measure' for appropriation request &V1&. However, you have not assi...
AO193
Model order &1 does not exist - please correct
What causes this issue? You want to create an order from the appropriation request using order type &V2&. Model order &V1& that is en...
AO194
Model order &1 has an incorrect order category &2 - please correct
What causes this issue? You want to assign order type &V1& to the appropriation request. Order category &V2& does not identify the or...