Do you have any question about this error?
Message type: E = Error
Message class: 7A - PS Progress Analysis
Message number: 307
Message text: There must be at least &2 progress versions in CO area &1
You want to copy parameters for earned value analysis created before
release 4.5A. However, the settings in Customizing (IMG) are not
complete. You have not defined enough progress versions.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_SYSTEMVERW' OBJECT DOKU ID TX
In all, there must be &v2& CO versions. Create the missing ones with
exclusive use '03' (earned value analysis).
<DS:SIMG.SIMG_CFMENUORK3OKEQ>Execute</>
In all, there must be &v2& progress versions in CO area &v1&. Create
the missing ones and fill in the necessary information. The progress
versions in CO area &v1& must have the same version numbers as those in
the other CO areas. <DS:SIMG.SIMG_OLPR_EVVS>Execute</>
Error message extract from SAP system. Copyright SAP SE.
7A307
- There must be at least &2 progress versions in CO area &1 ?The SAP error message 7A307 indicates that there must be at least a specified number of progress versions in a controlling (CO) area. This error typically arises in the context of controlling area settings, particularly when dealing with internal orders, cost centers, or other CO-related objects.
Cause:
The error occurs when the system expects a minimum number of progress versions to be defined for a specific controlling area, but the required number is not met. This can happen due to:
- Configuration Issues: The controlling area may not be properly configured to have the required number of progress versions.
- Missing Data: There may be missing or incomplete data entries for the progress versions in the controlling area.
- System Settings: The system settings or parameters may not be aligned with the business requirements, leading to this error.
Solution:
To resolve the error, you can take the following steps:
Check Configuration:
- Go to the configuration settings for the controlling area in SAP.
- Ensure that the required number of progress versions is defined. You can do this by navigating to the relevant configuration path in the SAP menu (usually under Controlling > Internal Orders or Cost Center Accounting).
Define Progress Versions:
- If the required progress versions are not defined, you will need to create them. This can typically be done in the configuration settings for the controlling area.
- Make sure to define the progress versions according to your business requirements.
Review Data Entries:
- Check if there are any missing entries or inconsistencies in the data related to progress versions.
- Ensure that all necessary data is entered correctly.
Consult Documentation:
- Refer to SAP documentation or help resources for specific guidance on configuring progress versions in your version of SAP.
Contact SAP Support:
- If the issue persists after checking the configuration and data entries, consider reaching out to SAP support for further assistance.
Related Information:
By following these steps, you should be able to identify the cause of the error and implement the necessary changes to resolve it.
Get instant SAP help. Start your 7-day free trial now.
7A306
Version &1 cannot be used as progress version
What causes this issue? You are trying to define a progress version for CO area &v2&. Version &v1& is not intended to be used as prog...
7A305
Progress version & defined (IMG)
What causes this issue? You want to edit parameters for earned value analysis. However, the settings in Customizing (IMG) are not complete. You have ...
7A308
Run this program again
What causes this issue? Some objects (projects or networks) could not be locked during the transfer of old earned value parameters to the new ones.Ho...
7A309
Data successfully transferred
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.