Do you have any question about this error?
Message type: E = Error
Message class: 6P - Messages for planned independent requirements (Appl.area 60)
Message number: 492
Message text: No requirement type exists for material &1 in plant &2
No valid requirements type could be determined.
This cause of this could be:
No strategy group has been maintained in the material master record.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
The system determines the valid requirements type from the strategy
group that was allocated in the material master record.
Check the possible cause of the error and maintain the appropriate
function.
Cause number 1 is maintained in the material master recod.
<DS:TRAN.MM02>Proceed</>
Error message extract from SAP system. Copyright SAP SE.
6P492
- No requirement type exists for material &1 in plant &2 ?The SAP error message 6P492 indicates that there is no requirement type defined for a specific material in a particular plant. This error typically arises in the context of production planning and material requirements planning (MRP) when the system is unable to find a valid requirement type for the specified material in the specified plant.
Cause:
- Missing Requirement Type: The primary cause of this error is that the requirement type for the material in the specified plant has not been defined in the system.
- Configuration Issues: There may be configuration issues in the MRP settings or the material master data.
- Material Master Data: The material may not be properly set up in the material master, particularly in the MRP views.
- Plant-Specific Settings: The requirement type may not be assigned to the specific plant for the material.
Solution:
To resolve this error, you can follow these steps:
Check Material Master Data:
- Go to the material master (transaction code
MM03
) and check the MRP views for the material in question.- Ensure that the material is set up correctly for the relevant plant.
Define Requirement Type:
- If the requirement type is missing, you need to define it. This can be done in the configuration settings:
- Use transaction code
SPRO
to access the SAP Reference IMG.- Navigate to Production ? Material Requirements Planning ? Master Data ? Define Requirement Types.
- Create or modify the requirement type as needed.
Assign Requirement Type to Material:
- After defining the requirement type, ensure that it is assigned to the material in the relevant plant.
- This can be done in the material master under the MRP views.
Check MRP Settings:
- Review the MRP settings for the plant to ensure that they are correctly configured.
- Check if the MRP type and other related settings are appropriate for the material.
Consult Documentation:
- If you are unsure about the requirement types or how to configure them, refer to SAP documentation or consult with your SAP functional consultant.
Related Information:
MM03
: Display Material MasterSPRO
: SAP Reference IMGBy following these steps, you should be able to resolve the error message 6P492 and ensure that the material can be processed correctly in the specified plant.
Get instant SAP help. Start your 7-day free trial now.
6P491
No items exist for deletion
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
6P490
Display only possible for items with material
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
6P493
Changes made in the planning time fence will be ignored (& - &)
What causes this issue? In Customizing, you determined that no new schedule lines can be created in the planning time fence, nor can existing schedul...
6P494
Material is blocked
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.